| Assessment Year | 2018 |
|---|---|
| Principal Product | Soy and Almond Milk |
| NAICS | 311511: Fluid Milk Manufacturing |
| SIC | 2026: Fluid Milk |
| Sales Range | $50 M to 100M |
| # of Employees | 90 |
| Plant Area |
1,000,000
ft2
|
| Annual Production | 25,000
Tgal
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $677,456 | 8,562,071 |
kWh
|
$0.079 | |
| Electricity Demand | $395,665 | 22,152 |
kW-mo/yr
|
$17.86 | |
| Natural Gas | $1,085,550 | 183,149 |
MMBtu
|
$5.93 | |
| Waste Disposal Costs | |||||
| Water Usage | $318,817 | 127,510,812 |
Tgal
|
$0.003 | |
| Water Disposal | $432,219 | 79,730 |
Tgal
|
$5.42 | |
| TOTAL YEARLY COSTS | $2,909,707 | ||||
| RECOMMENDED SAVINGS* | $305,856 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $120,594 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,768 | $350 |
$8,768
110,821
kWh
|
- | - | - | - | - | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,647 | $300 |
$1,977
24,985
kWh
|
$670
-
kW-mo/yr
|
- | - | - | - | - | |
| 03 | 2.2163: Use minimum steam operating pressure | $875 | $200 | - | - |
$875
-
MMBtu
|
- | - | - | - | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $653 | $187 |
$499
6,313
kWh
|
$154
-
kW-mo/yr
|
- | - | - | - | - | |
| 05 | 2.2135: Repair and eliminate steam leaks | $488 | $200 | - | - |
$488
-
MMBtu
|
- | - | - | - | |
| 06 | 2.2136: Install / repair insulation on steam lines | $906 | $468 | - | - |
$906
-
MMBtu
|
- | - | - | - | |
| 07 | 2.2621: Modify refrigeration system to operate at a lower pressure | $32,827 | $20,000 |
$32,827
414,902
kWh
|
- | - | - | - | - | - | |
| 08 | 2.2628: Utilize a less expensive cooling method | $28,367 | $15,956 |
$21,667
273,856
kWh
|
$6,700
-
kW-mo/yr
|
- | - | - | - | - | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $43,509 | $36,186 |
$32,120
405,969
kWh
|
$12,483
-
kW-mo/yr
|
- | - | - | $1,747 | $(-2,841.0) | |
| 10 | 2.2121: Increase amount of condensate returned | $17,989 | $48,803 |
$(-958.0)
(-12,108)
kWh
|
- |
$7,734
-
MMBtu
|
$3,539
-
Tgal
|
$7,674
-
Tgal
|
- | - | |
| 11 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,207 | $7,506 |
$2,207
27,889
kWh
|
- | - | - | - | - | - | |
| 12 | 2.1224: Replace boiler | $110,920 | $948,704 |
$(-920.0)
(-11,632)
kWh
|
$(-333.0)
-
kW-mo/yr
|
$98,173
-
MMBtu
|
- | - | - | $14,000 | |
| 13 | 3.5131: Recycle white water | $55,700 | $17,768 |
$(-712.0)
(-9,002)
kWh
|
$(-343.0)
-
kW-mo/yr
|
- |
$17,915
-
Tgal
|
$38,840
-
Tgal
|
- | - | |
| TOTAL RECOMMENDED | $305,856 | $1,096,628 |
$97,475
1,231,993
kWh
|
$19,331
-
kW-mo/yr
|
$108,176
-
MMBtu
|
$21,454
-
Tgal
|
$46,514
-
Tgal
|
$1,747 | $11,159 | ||
| TOTAL IMPLEMENTED | $120,594 | $81,166 |
$99,566
1,258,422
kWh
|
$19,853
-
kW-mo/yr
|
$2,269
-
MMBtu
|
- | - | $1,747 | $(-2,841.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs