ITAC Assessment: SF0516
ITAC logo
ITAC Assessment: SF0516
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Soy and Almond Milk
NAICS 311511: Fluid Milk Manufacturing
SIC 2026: Fluid Milk
Sales Range $50
M
to 100
M
# of Employees 90
Plant Area 1,000,000
ft2
Annual Production 25,000
Tgal
Production Hrs. Annual 7,488
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $677,456 8,562,071
kWh
Electricity Demand $395,665 22,152
kW-mo/yr
Natural Gas $1,085,550 183,149
MMBtu
Waste Disposal Costs
Water Usage $318,817 127,510,812
Tgal
Water Disposal $432,219 79,730
Tgal
TOTAL YEARLY COSTS $2,909,707
RECOMMENDED SAVINGS* $305,856 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $120,594

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,768 $350 $8,768
110,821
kWh
- - - - - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $2,647 $300 $1,977
24,985
kWh
$670
-
kW-mo/yr
- - - - -
03 2.2163: Use minimum steam operating pressure $875 $200 - - $875
-
MMBtu
- - - -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $653 $187 $499
6,313
kWh
$154
-
kW-mo/yr
- - - - -
05 2.2135: Repair and eliminate steam leaks $488 $200 - - $488
-
MMBtu
- - - -
06 2.2136: Install / repair insulation on steam lines $906 $468 - - $906
-
MMBtu
- - - -
07 2.2621: Modify refrigeration system to operate at a lower pressure $32,827 $20,000 $32,827
414,902
kWh
- - - - - -
08 2.2628: Utilize a less expensive cooling method $28,367 $15,956 $21,667
273,856
kWh
$6,700
-
kW-mo/yr
- - - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $43,509 $36,186 $32,120
405,969
kWh
$12,483
-
kW-mo/yr
- - - $1,747 $(-2,841.0)
10 2.2121: Increase amount of condensate returned $17,989 $48,803 $(-958.0)
(-12,108)
kWh
- $7,734
-
MMBtu
$3,539
-
Tgal
$7,674
-
Tgal
- -
11 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,207 $7,506 $2,207
27,889
kWh
- - - - - -
12 2.1224: Replace boiler $110,920 $948,704 $(-920.0)
(-11,632)
kWh
$(-333.0)
-
kW-mo/yr
$98,173
-
MMBtu
- - - $14,000
13 3.5131: Recycle white water $55,700 $17,768 $(-712.0)
(-9,002)
kWh
$(-343.0)
-
kW-mo/yr
- $17,915
-
Tgal
$38,840
-
Tgal
- -
TOTAL RECOMMENDED $305,856 $1,096,628 $97,475
1,231,993
kWh
$19,331
-
kW-mo/yr
$108,176
-
MMBtu
$21,454
-
Tgal
$46,514
-
Tgal
$1,747 $11,159
TOTAL IMPLEMENTED $120,594 $81,166 $99,566
1,258,422
kWh
$19,853
-
kW-mo/yr
$2,269
-
MMBtu
- - $1,747 $(-2,841.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs