Assessment Year | 2017 |
---|---|
Principal Product | wastewater, recycled water |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $10 M to 50M |
# of Employees | 25 |
Plant Area |
741,826
ft2
|
Annual Production | 3,250,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $830,560 | 8,174,462 |
kWh
|
$0.10 |
Electricity Demand | $337,325 | 15,086 |
kW-mo/yr
|
$22.36 |
TOTAL YEARLY COSTS | $1,167,885 | |||
RECOMMENDED SAVINGS* | $207,474 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $26,126 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $852 | $90 |
$655
6,446
kWh
|
$197
-
kW-mo/yr
|
- | - | - | |
02 | 2.6231: Utilize controls to operate equipment only when needed | $1,991 | $546 |
$1,991
19,605
kWh
|
- | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $22,454 | $23,168 |
$19,293
189,893
kWh
|
$3,505
-
kW-mo/yr
|
- | $1,585 | $(-1,929.0) | |
04 | 2.7135: Install occupancy sensors | $1,681 | $3,001 |
$1,277
12,567
kWh
|
$404
-
kW-mo/yr
|
- | - | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,437 | $21,315 |
$4,947
48,690
kWh
|
$1,490
-
kW-mo/yr
|
- | - | - | |
06 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $4,855 | $20,327 |
$4,855
47,785
kWh
|
- | - | - | - | |
07 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $169,204 | $790,554 |
$272,383
2,680,938
kWh
|
$82,397
-
kW-mo/yr
|
$(-59,003.0)
-
MMBtu
|
$(-126,573.0) | - | |
TOTAL RECOMMENDED | $207,474 | $859,001 |
$305,401
3,005,924
kWh
|
$87,993
-
kW-mo/yr
|
$(-59,003.0)
-
MMBtu
|
$(-124,988.0) | $(-1,929.0) | ||
TOTAL IMPLEMENTED | $26,126 | $26,715 |
$22,561
222,065
kWh
|
$3,909
-
kW-mo/yr
|
- | $1,585 | $(-1,929.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs