ITAC Assessment: SF0487
ITAC logo
ITAC Assessment: SF0487
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Lactose and Whey Protein
NAICS 311513: Cheese Manufacturing
SIC 2022: Natural, Processed, and Imitation Cheese
Sales Range $10
M
to 50
M
# of Employees 58
Plant Area 250,000
ft2
Annual Production 74,000
ton
Production Hrs. Annual 8,760
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,899,531 24,338,244
kWh
Electricity Demand $633,724 39,276
kW-mo/yr
TOTAL YEARLY COSTS $2,533,255
RECOMMENDED SAVINGS* $75,646 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,094

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.7224: Reduce space conditioning during non-working hours $5,356 - $3,489
44,690
kWh
- $1,867
-
MMBtu
- -
02 2.6212: Turn off equipment during breaks, reduce operating time $13,545 - $10,556
135,208
kWh
$2,989
-
kW-mo/yr
- - -
03 2.2511: Insulate bare equipment $2,132 $534 - - $2,132
-
MMBtu
- -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $24,944 $11,650 $24,944
319,507
kWh
- - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $18,738 $17,574 $15,361
196,763
kWh
$4,130
-
kW-mo/yr
- $635 $(-1,388.0)
06 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $3,794 $3,610 $3,794
48,596
kWh
- - - -
07 2.7135: Install occupancy sensors $7,137 $27,407 $5,891
75,454
kWh
$1,246
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $75,646 $60,775 $64,035
820,218
kWh
$8,365
-
kW-mo/yr
$3,999
-
MMBtu
$635 $(-1,388.0)
TOTAL IMPLEMENTED $24,094 $17,574 $18,850
241,453
kWh
$4,130
-
kW-mo/yr
$1,867
-
MMBtu
$635 $(-1,388.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs