ITAC Assessment: SF0485
ITAC logo
ITAC Assessment: SF0485
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Finished Wines
NAICS 312130: Wineries
SIC 2084: Wines, Brandy, and Brandy Spirits
Sales Range $10
M
to 50
M
# of Employees 350
Plant Area 6,534,000
ft2
Annual Production 150,000
ton
Production Hrs. Annual 7,104
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,126,219 12,341,019
kWh
Electricity Demand $992,859 33,794
kW-mo/yr
Natural Gas $65,465 10,856
MMBtu
TOTAL YEARLY COSTS $2,184,543
RECOMMENDED SAVINGS* $188,612 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $93,406

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $5,701 - - - $5,701 - - - -
02 2.6212: Turn off equipment during breaks, reduce operating time $4,294 - $1,226
13,428
kWh
$3,068
-
kW-mo/yr
- - - - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,665 - $3,745
41,032
kWh
- - - - $(-1,080.0) -
04 2.2123: Insulate feedwater tank $1,749 $272 - - - $1,749
-
MMBtu
- - -
05 2.2623: Minimize condenser cooling water temperature $40,459 $14,272 $40,459
443,335
kWh
- - - - - -
06 2.4226: Use / purchase optimum sized compressor $34,411 $26,609 $21,701
237,796
kWh
$12,710
-
kW-mo/yr
- - - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $75,614 $154,359 $65,009
712,352
kWh
$10,424
-
kW-mo/yr
- - $4,243 - $(-4,062.0)
08 2.7135: Install occupancy sensors $5,132 $16,334 $2,840
31,116
kWh
$2,292
-
kW-mo/yr
- - - - -
09 2.4239: Eliminate or reduce compressed air usage $6,358 $22,334 $4,412
48,348
kWh
$1,946
-
kW-mo/yr
- - - - -
10 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,976 $13,984 $2,325
25,471
kWh
$1,651
-
kW-mo/yr
- - - - -
11 2.2511: Insulate bare equipment $4,740 $17,316 $4,740
51,935
kWh
- - - - - -
12 2.2414: Use waste heat from hot flue gases to preheat $3,513 $14,174 - - - $3,513
-
MMBtu
- - -
TOTAL RECOMMENDED $188,612 $279,654 $146,457
1,604,813
kWh
$32,091
-
kW-mo/yr
$5,701 $5,262
-
MMBtu
$4,243 $(-1,080.0) $(-4,062.0)
TOTAL IMPLEMENTED $93,406 $170,693 $72,820
797,928
kWh
$15,784
-
kW-mo/yr
$5,701 - $4,243 $(-1,080.0) $(-4,062.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs