Assessment Year | 2016 |
---|---|
Principal Product | Non-Carbonated Beverages |
NAICS | 311421: Fruit and Vegetable Canning |
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $10 M to 50M |
# of Employees | 192 |
Plant Area |
387,000
ft2
|
Annual Production | 47,000
units
|
Production Hrs. Annual | 7,248
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $647,031 | 5,997,816 |
kWh
|
$0.11 |
Electricity Demand | $552,243 | 18,864 |
kW-mo/yr
|
$29.27 |
Natural Gas | $778,045 | 140,333 |
MMBtu
|
$5.54 |
Other Energy | $748,172 | 5,282,671 |
MMBtu
|
$0.14 |
TOTAL YEARLY COSTS | $2,725,491 | |||
RECOMMENDED SAVINGS* | $247,116 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $81,221 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,477 | $140 |
$3,089
28,637
kWh
|
$1,388
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $10,662 | - | - | - | $10,662 | - | - | - | |
03 | 2.7224: Reduce space conditioning during non-working hours | $16,033 | - |
$9,576
88,767
kWh
|
- | - |
$6,457
-
MMBtu
|
- | - | |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $5,008 | - | - | - | - |
$10,008
-
MMBtu
|
$(-5,000.0) | - | |
05 | 2.6218: Turn off equipment when not in use | $23,373 | - |
$23,373
216,661
kWh
|
- | - | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $908 | $105 |
$328
3,044
kWh
|
$148
-
kW-mo/yr
|
- | - | $19 | $413 | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,030 | $208 |
$716
6,635
kWh
|
$314
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.2692: Use outside cold water source as a supply of cooling water | $119,304 | $36,151 |
$82,947
768,886
kWh
|
$36,357
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.4224: Upgrade controls on compressors | $48,481 | $18,682 |
$48,481
449,401
kWh
|
- | - | - | - | - | |
10 | 2.2511: Insulate bare equipment | $660 | $769 | - | - | - |
$660
-
MMBtu
|
- | - | |
11 | 2.2414: Use waste heat from hot flue gases to preheat | $7,601 | $10,000 | - | - | - |
$7,601
-
MMBtu
|
- | - | |
12 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,674 | $10,567 |
$4,640
43,012
kWh
|
$2,034
-
kW-mo/yr
|
- | - | - | - | |
13 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $2,905 | $11,333 | - | - | - |
$2,905
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $247,116 | $87,955 |
$173,150
1,605,043
kWh
|
$40,241
-
kW-mo/yr
|
$10,662 |
$27,631
-
MMBtu
|
$(-4,981.0) | $413 | ||
TOTAL IMPLEMENTED | $81,221 | $19,696 |
$61,474
569,849
kWh
|
$1,536
-
kW-mo/yr
|
$10,662 |
$7,117
-
MMBtu
|
$19 | $413 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs