ITAC Assessment: SF0481
ITAC logo
ITAC Assessment: SF0481
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Non-Carbonated Beverages
NAICS 311421: Fruit and Vegetable Canning
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $10
M
to 50
M
# of Employees 192
Plant Area 387,000
ft2
Annual Production 47,000
units
Production Hrs. Annual 7,248
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $647,031 5,997,816
kWh
Electricity Demand $552,243 18,864
kW-mo/yr
Natural Gas $778,045 140,333
MMBtu
Other Energy $748,172 5,282,671
MMBtu
TOTAL YEARLY COSTS $2,725,491
RECOMMENDED SAVINGS* $247,116 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $81,221

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $4,477 $140 $3,089
28,637
kWh
$1,388
-
kW-mo/yr
- - - -
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $10,662 - - - $10,662 - - -
03 2.7224: Reduce space conditioning during non-working hours $16,033 - $9,576
88,767
kWh
- - $6,457
-
MMBtu
- -
04 2.1233: Analyze flue gas for proper air/fuel ratio $5,008 - - - - $10,008
-
MMBtu
$(-5,000.0) -
05 2.6218: Turn off equipment when not in use $23,373 - $23,373
216,661
kWh
- - - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $908 $105 $328
3,044
kWh
$148
-
kW-mo/yr
- - $19 $413
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,030 $208 $716
6,635
kWh
$314
-
kW-mo/yr
- - - -
08 2.2692: Use outside cold water source as a supply of cooling water $119,304 $36,151 $82,947
768,886
kWh
$36,357
-
kW-mo/yr
- - - -
09 2.4224: Upgrade controls on compressors $48,481 $18,682 $48,481
449,401
kWh
- - - - -
10 2.2511: Insulate bare equipment $660 $769 - - - $660
-
MMBtu
- -
11 2.2414: Use waste heat from hot flue gases to preheat $7,601 $10,000 - - - $7,601
-
MMBtu
- -
12 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,674 $10,567 $4,640
43,012
kWh
$2,034
-
kW-mo/yr
- - - -
13 2.1243: Use heat from boiler blowdown to preheat boiler feed water $2,905 $11,333 - - - $2,905
-
MMBtu
- -
TOTAL RECOMMENDED $247,116 $87,955 $173,150
1,605,043
kWh
$40,241
-
kW-mo/yr
$10,662 $27,631
-
MMBtu
$(-4,981.0) $413
TOTAL IMPLEMENTED $81,221 $19,696 $61,474
569,849
kWh
$1,536
-
kW-mo/yr
$10,662 $7,117
-
MMBtu
$19 $413
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs