Assessment Year | 2016 |
---|---|
Principal Product | Steel Castings |
NAICS | 331513: Steel Foundries (except Investment) |
SIC | 3325: Steel Foundries, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 250 |
Plant Area |
175,000
ft2
|
Annual Production | 5,050
ton
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,532,532 | 23,781,908 |
kWh
|
$0.11 |
Electricity Demand | $2,129,911 | 132,132 |
kW-mo/yr
|
$16.12 |
Electricity Fees | $415,263 | - |
|
- |
Natural Gas | $791,367 | 144,041 |
MMBtu
|
$5.49 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $125,907 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $105,274 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,871 | - |
$8,871
114,858
kWh
|
- | - | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,100 | $280 |
$5,640
52,963
kWh
|
$2,460
-
kW-mo/yr
|
- | - | - | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,817 | - | - | - | $5,817 | - | - | |
04 | 2.6218: Turn off equipment when not in use | $8,163 | $913 |
$8,163
76,663
kWh
|
- | - | - | - | |
05 | 2.6231: Utilize controls to operate equipment only when needed | $9,486 | $722 |
$9,486
89,081
kWh
|
- | - | - | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,722 | $386 |
$1,894
17,782
kWh
|
$828
-
kW-mo/yr
|
- | - | - | |
07 | 2.6218: Turn off equipment when not in use | $1,324 | $215 |
$1,096
10,293
kWh
|
$228
-
kW-mo/yr
|
- | - | - | |
08 | 2.4239: Eliminate or reduce compressed air usage | $3,971 | $4,378 |
$2,765
25,963
kWh
|
$1,206
-
kW-mo/yr
|
- | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $63,239 | $121,403 |
$44,939
422,004
kWh
|
$17,865
-
kW-mo/yr
|
- | $1,892 | $(-1,457.0) | |
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,176 | $17,481 |
$7,176
67,387
kWh
|
- | - | - | - | |
11 | 2.7135: Install occupancy sensors | $7,038 | $21,100 |
$3,736
35,082
kWh
|
$3,302
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $125,907 | $166,878 |
$93,766
912,076
kWh
|
$25,889
-
kW-mo/yr
|
$5,817 | $1,892 | $(-1,457.0) | ||
TOTAL IMPLEMENTED | $105,274 | $144,297 |
$74,339
729,645
kWh
|
$24,683
-
kW-mo/yr
|
$5,817 | $1,892 | $(-1,457.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs