ITAC Assessment: SF0470
ITAC logo
ITAC Assessment: SF0470
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product bread and muffins
NAICS 311812: Commercial Bakeries
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 86,679
ft2
Annual Production 70,000,000
lb
Production Hrs. Annual 7,488
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $552,779 5,947,277
kWh
Electricity Demand $310,391 11,480
kW-mo/yr
Natural Gas $362,933 53,424
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $143,132 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $143,132

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $10,220 $4,488 $7,083
76,198
kWh
$3,137
-
kW-mo/yr
- - - -
02 2.6231: Utilize controls to operate equipment only when needed $5,421 $3,541 $5,421
58,318
kWh
- - - - -
03 2.2121: Increase amount of condensate returned $26,563 $30,811 - - $14,293
-
MMBtu
- - $12,270
-
Tgal
04 2.2414: Use waste heat from hot flue gases to preheat $5,546 $11,844 - - $5,546
-
MMBtu
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $4,206 $17,797 $3,834
41,246
kWh
- - $598 $(-226.0) -
06 2.9114: Use solar heat to make electricty $91,176 $450,224 $52,052
559,997
kWh
$39,124
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $143,132 $518,705 $68,390
735,759
kWh
$42,261
-
kW-mo/yr
$19,839
-
MMBtu
$598 $(-226.0) $12,270
-
Tgal
TOTAL IMPLEMENTED $143,132 $518,705 $68,390
735,759
kWh
$42,261
-
kW-mo/yr
$19,839
-
MMBtu
$598 $(-226.0) $12,270
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs