ITAC Assessment: SF0431
ITAC logo
ITAC Assessment: SF0431
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Treated Water
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range less than $500
k
# of Employees 58
Plant Area 900,000
ft2
Annual Production 2,555,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $449,568 5,548,874
kWh
Electricity Demand $177,468 10,067
kW-mo/yr
Electricity Fees $18,037 -
Natural Gas $18,768 2,123
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $120,709 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $35,478

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7224: Reduce space conditioning during non-working hours $3,402 - $3,402
41,242
kWh
- -
02 2.4131: Size electric motors for peak operating efficiency $35,740 $12,095 $27,372
331,786
kWh
$8,368
-
kW-mo/yr
-
03 2.6218: Turn off equipment when not in use $24,335 $6,137 $24,335
294,965
kWh
- -
04 2.6232: Install set-back timers $535 $210 $535
6,482
kWh
- -
05 2.7131: Add area lighting switches $10,130 $19,788 $6,704
81,258
kWh
$3,426
-
kW-mo/yr
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $25,348 $83,669 $21,879
265,195
kWh
$3,469
-
kW-mo/yr
-
07 2.7232: Replace existing hvac unit with high efficiency model $1,616 $9,150 $1,071
12,985
kWh
$955
-
kW-mo/yr
$(-410.0)
-
MMBtu
08 2.4322: Use or replace with energy efficient substitutes $19,603 $121,742 $15,013
181,972
kWh
$4,590
-
kW-mo/yr
-
TOTAL RECOMMENDED $120,709 $252,791 $100,311
1,215,885
kWh
$20,808
-
kW-mo/yr
$(-410.0)
-
MMBtu
TOTAL IMPLEMENTED $35,478 $103,457 $28,583
346,453
kWh
$6,895
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs