Assessment Year | 2012 |
---|---|
Principal Product | Canned Tomatoes |
NAICS | 311421: Fruit and Vegetable Canning |
SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
Sales Range | $100 M to 500M |
# of Employees | 650 |
Plant Area |
3,354,120
ft2
|
Annual Production | 350,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,521,149 | 17,595,933 |
kWh
|
$0.086 |
Electricity Demand | $589,282 | 39,077 |
kW-mo/yr
|
$15.08 |
Electricity Fees | $24,466 | - |
|
- |
Natural Gas | $2,961,587 | 785,423 |
MMBtu
|
$3.77 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $221,282 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $83,604 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2153: Close off unneeded steam lines | $417 | - | - | - |
$417
-
MMBtu
|
- | - | - | - | |
02 | 2.2135: Repair and eliminate steam leaks | $4,512 | - | - | - |
$4,512
-
MMBtu
|
- | - | - | - | |
03 | 2.6232: Install set-back timers | $3,656 | - |
$2,063
23,878
kWh
|
- |
$1,593
-
MMBtu
|
- | - | - | - | |
04 | 2.2113: Repair or replace steam traps | $5,375 | $3,925 | - | - |
$5,375
-
MMBtu
|
- | - | - | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,157 | $5,079 |
$7,157
82,831
kWh
|
- | - | - | - | - | - | |
06 | 2.2511: Insulate bare equipment | $4,091 | $4,108 | - | - |
$4,091
-
MMBtu
|
- | - | - | - | |
07 | 2.7135: Install occupancy sensors | $14,919 | $21,094 |
$12,653
146,443
kWh
|
$2,266
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $406 | $1,040 | - | - |
$406
-
MMBtu
|
- | - | - | - | |
09 | 2.2511: Insulate bare equipment | $2,993 | $7,655 | - | - |
$2,993
-
MMBtu
|
- | - | - | - | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $42,535 | $127,175 |
$31,046
359,324
kWh
|
$7,863
-
kW-mo/yr
|
- | - | $1,199 | - | $2,427 | |
11 | 2.3411: Replace electric motors with back pressure steam turbines and use exhaust steam for process heat | $104,307 | $469,980 |
$82,366
953,313
kWh
|
$21,941
-
kW-mo/yr
|
- | - | - | - | - | |
12 | 3.4115: Recover and reuse cooling water | $4,700 | $700 | - | - | - |
$4,700
-
Tgal
|
- | - | - | |
13 | 4.132: Purchase new equipment to reduce material use / cost | $26,214 | $85,490 | - | - | - | - | - | $26,214 | - | |
TOTAL RECOMMENDED | $221,282 | $726,246 |
$135,285
1,565,789
kWh
|
$32,070
-
kW-mo/yr
|
$19,387
-
MMBtu
|
$4,700
-
Tgal
|
$1,199 | $26,214 | $2,427 | ||
TOTAL IMPLEMENTED | $83,604 | $165,697 |
$45,762
529,645
kWh
|
$10,129
-
kW-mo/yr
|
$19,387
-
MMBtu
|
$4,700
-
Tgal
|
$1,199 | - | $2,427 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs