ITAC Assessment: SF0421
ITAC logo
ITAC Assessment: SF0421
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Wood Pallets
NAICS 321920: Wood Container and Pallet Manufacturing
SIC 2448: Wood Pallets and Skids
Sales Range $10
M
to 50
M
# of Employees 118
Plant Area 773,190
ft2
Annual Production 400,000
pieces
Production Hrs. Annual 3,180
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,826 514,036
kWh
Electricity Demand $28,210 2,556
kW-mo/yr
Electricity Fees $9,849 -
LPG $154,841 6,004
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $53,615 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,100

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.7224: Reduce space conditioning during non-working hours $6,912 - $1,066
9,752
kWh
- $5,846
-
MMBtu
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,017 - $3,017
55,339
kWh
- - - - -
03 2.1131: Repair faulty insulation in furnaces, boilers, etc $5,494 $10,564 - - $5,494
-
MMBtu
- - -
04 2.8114: Change rate schedules or other changes in utility service $24,965 $104,550 - - - - $24,965 -
05 2.6231: Utilize controls to operate equipment only when needed $8,801 $22,991 $5,516
79,143
kWh
$3,285
-
kW-mo/yr
- - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $4,282 $29,386 $3,108
43,389
kWh
$765
-
kW-mo/yr
- $163 - $246
07 2.4231: Reduce the pressure of compressed air to the minimum required $144 $70 $114
1,638
kWh
$30
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $53,615 $167,561 $12,821
189,261
kWh
$4,080
-
kW-mo/yr
$11,340
-
MMBtu
$163 $24,965 $246
TOTAL IMPLEMENTED $16,100 $52,377 $11,641
177,871
kWh
$4,050
-
kW-mo/yr
- $163 - $246
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs