Assessment Year | 2012 |
---|---|
Principal Product | Wood Pallets |
NAICS | 321920: Wood Container and Pallet Manufacturing |
SIC | 2448: Wood Pallets and Skids |
Sales Range | $10 M to 50M |
# of Employees | 118 |
Plant Area |
773,190
ft2
|
Annual Production | 400,000
pieces
|
Production Hrs. Annual | 3,180
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $38,826 | 514,036 |
kWh
|
$0.076 |
Electricity Demand | $28,210 | 2,556 |
kW-mo/yr
|
$11.04 |
Electricity Fees | $9,849 | - |
|
- |
LPG | $154,841 | 6,004 |
MMBtu
|
$25.79 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $53,615 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,100 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7224: Reduce space conditioning during non-working hours | $6,912 | - |
$1,066
9,752
kWh
|
- |
$5,846
-
MMBtu
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,017 | - |
$3,017
55,339
kWh
|
- | - | - | - | - | |
03 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $5,494 | $10,564 | - | - |
$5,494
-
MMBtu
|
- | - | - | |
04 | 2.8114: Change rate schedules or other changes in utility service | $24,965 | $104,550 | - | - | - | - | $24,965 | - | |
05 | 2.6231: Utilize controls to operate equipment only when needed | $8,801 | $22,991 |
$5,516
79,143
kWh
|
$3,285
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,282 | $29,386 |
$3,108
43,389
kWh
|
$765
-
kW-mo/yr
|
- | $163 | - | $246 | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $144 | $70 |
$114
1,638
kWh
|
$30
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $53,615 | $167,561 |
$12,821
189,261
kWh
|
$4,080
-
kW-mo/yr
|
$11,340
-
MMBtu
|
$163 | $24,965 | $246 | ||
TOTAL IMPLEMENTED | $16,100 | $52,377 |
$11,641
177,871
kWh
|
$4,050
-
kW-mo/yr
|
- | $163 | - | $246 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs