Assessment Year | 2010 |
---|---|
Principal Product | Composition Roofing |
NAICS | 324122: Asphalt Shingle and Coating Materials Manufacturing |
SIC | 2952: Asphalt Felts and Coatings |
Sales Range | $5 M to 10M |
# of Employees | 31 |
Plant Area |
60,235
ft2
|
Annual Production | 1
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $148,895 | 930,600 |
kWh
|
$0.16 |
Natural Gas | $141,866 | 17,346 |
MMBtu
|
$8.18 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $27,488 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $22,344 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $5,144 | - | - | $5,144 | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $747 | - |
$747
4,222
kWh
|
- | - | |
03 | 2.7134: Use photocell controls | $7,756 | $1,353 |
$7,756
43,821
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,874 | $1,627 |
$1,874
10,547
kWh
|
- | - | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $5,964 | $7,727 | - | - |
$5,964
-
MMBtu
|
|
06 | 2.2515: Use optimum thickness insulation | $791 | $1,536 | - | - |
$791
-
MMBtu
|
|
07 | 2.4226: Use / purchase optimum sized compressor | $397 | $798 |
$397
2,246
kWh
|
- | - | |
08 | 2.4133: Use most efficient type of electric motors | $1,393 | $2,851 |
$1,393
7,838
kWh
|
- | - | |
09 | 2.7135: Install occupancy sensors | $920 | $2,132 |
$920
5,202
kWh
|
- | - | |
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,160 | $3,840 |
$1,160
6,557
kWh
|
- | - | |
11 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,342 | $6,259 |
$1,342
7,584
kWh
|
- | - | |
TOTAL RECOMMENDED | $27,488 | $28,123 |
$15,589
88,017
kWh
|
$5,144 |
$6,755
-
MMBtu
|
||
TOTAL IMPLEMENTED | $22,344 | $28,123 |
$15,589
88,017
kWh
|
- |
$6,755
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs