Assessment Year | 2020 |
---|---|
Principal Product | Bakery Products |
NAICS | 311812: Commercial Bakeries |
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $5 M to 10M |
# of Employees | 77 |
Plant Area |
42,000
ft2
|
Annual Production | 1,300,000
units
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $44,223 | 1,051,920 |
kWh
|
$0.042 | |
Electricity Demand | $39,992 | 4,184 |
kW-mo/yr
|
$9.56 | |
Electricity Fees | $24,643 | - |
|
- | |
Natural Gas | $85,451 | 14,943 |
MMBtu
|
$5.72 | |
Waste Disposal Costs | |||||
Water Usage | $27,120 | 4,502 |
Tgal
|
$6.02 | |
TOTAL YEARLY COSTS | $221,429 | ||||
RECOMMENDED SAVINGS* | $11,853 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $8,145 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,708 | $1,550 |
$2,457
53,411
kWh
|
$1,251
-
kW-mo/yr
|
- | - | - | |
02 | 2.4224: Upgrade controls on compressors | $3,534 | $3,368 |
$2,332
50,710
kWh
|
$1,202
-
kW-mo/yr
|
- | - | - | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,729 | $410 | - | - |
$3,209
-
MMBtu
|
$(-480.0) | - | |
04 | 2.6125: Keep equipment clean | $991 | $464 |
$991
21,543
kWh
|
- | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $891 | $397 |
$159
3,454
kWh
|
$81
-
kW-mo/yr
|
- | - | $651 | |
TOTAL RECOMMENDED | $11,853 | $6,189 |
$5,939
129,118
kWh
|
$2,534
-
kW-mo/yr
|
$3,209
-
MMBtu
|
$(-480.0) | $651 | ||
TOTAL IMPLEMENTED | $8,145 | $4,639 |
$3,482
75,707
kWh
|
$1,283
-
kW-mo/yr
|
$3,209
-
MMBtu
|
$(-480.0) | $651 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs