| Assessment Year | 2010 |
|---|---|
| Principal Product | Pistachios |
| NAICS | 311911: Roasted Nuts and Peanut Butter Manufacturing |
| SIC | 2068: Salted and Roasted Nuts and Seeds |
| Sales Range | $10 M to 50M |
| # of Employees | 140 |
| Plant Area |
82,000
ft2
|
| Annual Production | 20,000,000
lb
|
| Production Hrs. Annual | 4,992
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $208,055 | 2,771,127 |
kWh
|
$0.075 |
| Electricity Demand | $75,779 | 7,766 |
kW-mo/yr
|
$9.76 |
| Electricity Fees | $(-38,933.0) | - |
|
- |
| Natural Gas | $204,925 | 26,155 |
MMBtu
|
$7.84 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $41,047 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7224: Reduce space conditioning during non-working hours | $10,471 | - |
$943
12,567
kWh
|
- |
$9,528
-
MMBtu
|
|
| 02 | 2.7134: Use photocell controls | $4,307 | $3,738 |
$2,700
35,958
kWh
|
$1,607
-
kW-mo/yr
|
- | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,677 | $1,600 |
$1,290
17,174
kWh
|
$387
-
kW-mo/yr
|
- | |
| 04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $3,507 | $7,500 |
$3,280
43,680
kWh
|
$1,687
-
kW-mo/yr
|
$(-1,460.0)
-
MMBtu
|
|
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,553 | $40,720 |
$9,047
120,460
kWh
|
$6,506
-
kW-mo/yr
|
- | |
| 06 | 2.7135: Install occupancy sensors | $5,315 | $18,821 |
$4,450
59,259
kWh
|
$865
-
kW-mo/yr
|
- | |
| 07 | 2.4133: Use most efficient type of electric motors | $217 | $461 |
$217
2,217
kWh
|
- | - | |
| TOTAL RECOMMENDED | $41,047 | $72,840 |
$21,927
291,315
kWh
|
$11,052
-
kW-mo/yr
|
$8,068
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs