ITAC Assessment: SF0386
ITAC logo
ITAC Assessment: SF0386
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Pistachios
NAICS 311911: Roasted Nuts and Peanut Butter Manufacturing
SIC 2068: Salted and Roasted Nuts and Seeds
Sales Range $10
M
to 50
M
# of Employees 140
Plant Area 82,000
ft2
Annual Production 20,000,000
lb
Production Hrs. Annual 4,992
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $208,055 2,771,127
kWh
Electricity Demand $75,779 7,766
kW-mo/yr
Electricity Fees $(-38,933.0) -
Natural Gas $204,925 26,155
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $41,047 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7224: Reduce space conditioning during non-working hours $10,471 - $943
12,567
kWh
- $9,528
-
MMBtu
02 2.7134: Use photocell controls $4,307 $3,738 $2,700
35,958
kWh
$1,607
-
kW-mo/yr
-
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,677 $1,600 $1,290
17,174
kWh
$387
-
kW-mo/yr
-
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $3,507 $7,500 $3,280
43,680
kWh
$1,687
-
kW-mo/yr
$(-1,460.0)
-
MMBtu
05 2.7142: Utilize higher efficiency lamps and/or ballasts $15,553 $40,720 $9,047
120,460
kWh
$6,506
-
kW-mo/yr
-
06 2.7135: Install occupancy sensors $5,315 $18,821 $4,450
59,259
kWh
$865
-
kW-mo/yr
-
07 2.4133: Use most efficient type of electric motors $217 $461 $217
2,217
kWh
- -
TOTAL RECOMMENDED $41,047 $72,840 $21,927
291,315
kWh
$11,052
-
kW-mo/yr
$8,068
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs