Assessment Year | 2009 |
---|---|
Principal Product | molded plastics |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 28 |
Plant Area |
12,000
ft2
|
Annual Production | 30,000,000
pieces
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $97,464 | 714,490 |
kWh
|
$0.14 |
Electricity Demand | $8,199 | 2,102 |
kW-mo/yr
|
$3.90 |
Electricity Fees | $12,612 | - |
|
- |
Natural Gas | $2,394 | 168 |
MMBtu
|
$14.25 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $28,764 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $707 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $707 | - |
$707
7,820
kWh
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,050 | $12,551 |
$8,949
65,606
kWh
|
$101
-
kW-mo/yr
|
|
03 | 2.4133: Use most efficient type of electric motors | $545 | $789 |
$522
3,828
kWh
|
$23
-
kW-mo/yr
|
|
04 | 2.7135: Install occupancy sensors | $765 | $1,142 |
$738
5,393
kWh
|
$27
-
kW-mo/yr
|
|
05 | 2.4224: Upgrade controls on compressors | $7,121 | $20,369 |
$7,121
52,201
kWh
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,009 | $17,634 |
$4,650
34,096
kWh
|
$359
-
kW-mo/yr
|
|
07 | 2.4321: Upgrade obsolete equipment | $5,567 | $24,469 |
$5,567
40,812
kWh
|
- | |
TOTAL RECOMMENDED | $28,764 | $76,954 |
$28,254
209,756
kWh
|
$510
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $707 | - |
$707
7,820
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs