Assessment Year | 2007 |
---|---|
Principal Product | Investment Castings |
NAICS | 331410: Nonferrous Metal (except Aluminum) Smelting and Refining |
SIC | 3339: Primary Smelting and Refining of Nonferrous Metals, Except Copper and Aluminum |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
55,000
ft2
|
Annual Production | 200,000
pieces
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $496,733 | 5,664,240 |
kWh
|
$0.088 |
Electricity Demand | $166,986 | 15,372 |
kW-mo/yr
|
$10.86 |
Electricity Fees | $39,414 | - |
|
- |
Natural Gas | $301,252 | 25,304 |
MMBtu
|
$11.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $112,228 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,679 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2135: Repair and eliminate steam leaks | $6,853 | - | - | - | - |
$6,853
-
MMBtu
|
|
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,603 | $150 |
$5,641
64,650
kWh
|
$962
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,755 | - |
$1,755
23,554
kWh
|
- | - | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $19,139 | $10,019 |
$19,139
259,384
kWh
|
- | - | - | |
05 | 2.7135: Install occupancy sensors | $3,490 | $1,992 |
$2,819
32,303
kWh
|
$671
-
kW-mo/yr
|
- | - | |
06 | 2.6231: Utilize controls to operate equipment only when needed | $725 | $757 |
$725
8,309
kWh
|
- | - | - | |
07 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $7,644 | $8,646 |
$13,416
153,753
kWh
|
$2,393
-
kW-mo/yr
|
- |
$(-8,165.0)
-
MMBtu
|
|
08 | 2.6231: Utilize controls to operate equipment only when needed | $2,042 | $2,339 |
$2,042
23,404
kWh
|
- | - | - | |
09 | 2.2514: Cover open tanks | $12,984 | $14,940 |
$12,984
148,792
kWh
|
- | - | - | |
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,554 | $4,281 |
$3,554
40,732
kWh
|
- | - | - | |
11 | 2.2414: Use waste heat from hot flue gases to preheat | $31,597 | $52,080 | - | - | - |
$31,597
-
MMBtu
|
|
12 | 2.7134: Use photocell controls | $3,302 | $9,569 |
$2,235
25,609
kWh
|
$1,067
-
kW-mo/yr
|
- | - | |
13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $335 | $980 |
$335
3,844
kWh
|
- | - | - | |
14 | 2.2414: Use waste heat from hot flue gases to preheat | $3,454 | $11,000 | - | - | - |
$3,454
-
MMBtu
|
|
15 | 2.8114: Change rate schedules or other changes in utility service | $8,751 | $37,915 | - | - | $8,751 | - | |
TOTAL RECOMMENDED | $112,228 | $154,668 |
$64,645
784,334
kWh
|
$5,093
-
kW-mo/yr
|
$8,751 |
$33,739
-
MMBtu
|
||
TOTAL IMPLEMENTED | $19,679 | $16,599 |
$11,088
130,507
kWh
|
$1,738
-
kW-mo/yr
|
- |
$6,853
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs