Assessment Year | 2006 |
---|---|
Principal Product | Disposable Laboratory Equipment |
NAICS | 339112: Surgical and Medical Instrument Manufacturing |
SIC | 3821: Laboratory Apparatus and Furniture |
Sales Range | less than $500 k |
# of Employees | 80 |
Plant Area |
53,000
ft2
|
Annual Production | 450,000
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $318,199 | 2,991,120 |
kWh
|
$0.11 |
Electricity Demand | $60,108 | 6,299 |
kW-mo/yr
|
$9.54 |
Electricity Fees | $57,178 | - |
|
- |
LPG | $2,173 | 1,394 |
MMBtu
|
$1.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $33,139 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $24,812 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.6231: Utilize controls to operate equipment only when needed | $4,466 | $169 |
$3,893
15,604
kWh
|
$573
-
kW-mo/yr
|
|
02 | 2.7241: Install outside air damper / economizer on hvac unit | $16,440 | $3,828 |
$16,440
154,556
kWh
|
- | |
03 | 2.3212: Optimize plant power factor | $3,422 | $1,950 |
$3,422
-
kWh
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,020 | $2,819 |
$3,200
22,370
kWh
|
$820
-
kW-mo/yr
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,535 | $4,389 |
$3,082
24,710
kWh
|
$453
-
kW-mo/yr
|
|
06 | 2.7135: Install occupancy sensors | $371 | $888 |
$254
2,391
kWh
|
$117
-
kW-mo/yr
|
|
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $885 | $2,838 |
$752
5,819
kWh
|
$133
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $33,139 | $16,881 |
$31,043
225,450
kWh
|
$2,096
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $24,812 | $9,274 |
$23,669
197,261
kWh
|
$1,143
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs