Assessment Year | 2006 |
---|---|
Principal Product | Salsa and Sauces |
NAICS | 311421: Fruit and Vegetable Canning |
SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
2,831,400
ft2
|
Annual Production | 4,000,000
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $219,489 | 2,226,000 |
kWh
|
$0.099 |
Electricity Demand | $67,222 | 8,128 |
kW-mo/yr
|
$8.27 |
Natural Gas | $314,025 | 41,152 |
MMBtu
|
$7.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $65,636 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $45,429 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2135: Repair and eliminate steam leaks | $494 | - | - | - |
$494
-
MMBtu
|
|
02 | 2.2511: Insulate bare equipment | $22,857 | $7,377 | - | - |
$22,857
-
MMBtu
|
|
03 | 2.4133: Use most efficient type of electric motors | $1,828 | $1,092 |
$1,618
15
kWh
|
$210
-
kW-mo/yr
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $1,506 | $1,461 |
$1,333
10,851
kWh
|
$173
-
kW-mo/yr
|
- | |
05 | 2.4239: Eliminate or reduce compressed air usage | $1,080 | $1,262 |
$959
9,205
kWh
|
$121
-
kW-mo/yr
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $17,338 | $24,888 |
$3,666
35,192
kWh
|
$472
-
kW-mo/yr
|
$13,200
-
MMBtu
|
|
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,894 | $3,026 |
$1,675
16,073
kWh
|
$219
-
kW-mo/yr
|
- | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,866 | $15,620 |
$5,734
55,037
kWh
|
$1,132
-
kW-mo/yr
|
- | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,234 | $9,460 |
$2,147
20,606
kWh
|
$1,087
-
kW-mo/yr
|
- | |
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $666 | $2,370 |
$562
5,391
kWh
|
$104
-
kW-mo/yr
|
- | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,873 | $33,600 |
$6,818
65,441
kWh
|
$1,055
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $65,636 | $100,156 |
$24,512
217,811
kWh
|
$4,573
-
kW-mo/yr
|
$36,551
-
MMBtu
|
||
TOTAL IMPLEMENTED | $45,429 | $43,186 |
$7,146
66,649
kWh
|
$1,732
-
kW-mo/yr
|
$36,551
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs