ITAC Assessment: SF0311
ITAC logo
ITAC Assessment: SF0311
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product cereal and powdered beverages
NAICS 311230: Breakfast Cereal Manufacturing
SIC 2043: Cereal Breakfast Foods
Sales Range $100
M
to 500
M
# of Employees 200
Plant Area 280,000
ft2
Annual Production 120,000,000
lb
Production Hrs. Annual 5,760
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $721,695 19,665,480
kWh
Electricity Demand $392,712 43,652
kW-mo/yr
Natural Gas $1,129,873 163,100
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $244,580 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $192,777

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.2135: Repair and eliminate steam leaks $133,918 - - - $133,918
-
MMBtu
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,048 - $5,048
535
kWh
- - - - -
03 2.4235: Remove or close off unneeded compressed air lines $1,110 - $1,110
103
kWh
- - - - -
04 2.2113: Repair or replace steam traps $24,768 $2,108 - - $24,768
-
MMBtu
- - -
05 2.7132: Install timers on light switches in little used areas $1,622 $504 $1,073
100
kWh
$549
-
kW-mo/yr
- - - -
06 2.4221: Install compressor air intakes in coolest locations $6,803 $2,959 $4,101
381
kWh
$2,702
-
kW-mo/yr
- - - -
07 2.4239: Eliminate or reduce compressed air usage $9,363 $6,375 $6,123
569
kWh
$3,240
-
kW-mo/yr
- - - -
08 2.7134: Use photocell controls $412 $480 $272
25
kWh
$140
-
kW-mo/yr
- - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $1,804 $2,332 $447
42
kWh
$150
-
kW-mo/yr
- - $1,207 -
10 2.1243: Use heat from boiler blowdown to preheat boiler feed water $3,402 $5,030 - - $3,402
-
MMBtu
- - -
11 2.4111: Utilize energy-efficient belts and other improved mechanisms $456 $693 $275
25
kWh
$181
-
kW-mo/yr
- - - -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $9,102 $18,405 $6,021
560
kWh
$3,081
-
kW-mo/yr
- - - -
13 2.4222: Install adequate dryers on air lines to eliminate blowdown $345 $658 $345
32
kWh
- - - - -
14 2.1243: Use heat from boiler blowdown to preheat boiler feed water $22,029 $46,851 - - $22,029
-
MMBtu
- - -
15 4.454: Modify startup/shutdown times $3,118 $13,200 - - - - - $3,118
16 3.1161: Eliminate/reduce an operation $1,600 - - - - $1,600
-
lb
- -
17 3.5217: Reuse / recycle/ sell paper products $19,680 $12,330 - - - $19,680
-
lb
- -
TOTAL RECOMMENDED $244,580 $111,925 $24,815
2,372
kWh
$10,043
-
kW-mo/yr
$184,117
-
MMBtu
$21,280
-
lb
$1,207 $3,118
TOTAL IMPLEMENTED $192,777 $20,813 $11,171
1,104
kWh
$3,240
-
kW-mo/yr
$158,686
-
MMBtu
$19,680
-
lb
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs