| Assessment Year | 2004 |
|---|---|
| Principal Product | Frozen and Canned Food |
| NAICS | 311422: Specialty Canning |
| SIC | 2032: Canned Specialties |
| Sales Range | $100 M to 500M |
| # of Employees | 700 |
| Plant Area |
100,000
ft2
|
| Annual Production | 4,500,000
pieces
|
| Production Hrs. Annual | 5,880
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,004,637 | 8,631,330 |
kWh
|
$0.12 |
| Electricity Demand | $238,634 | 18,916 |
kW-mo/yr
|
$12.62 |
| Natural Gas | $367,504 | 54,759 |
MMBtu
|
$6.71 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $384,226 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $136,081 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,759 | - |
$2,759
30,923
kWh
|
- | - | - | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $1,304 | - |
$1,104
9,804
kWh
|
$200
-
kW-mo/yr
|
- | - | |
| 03 | 2.6231: Utilize controls to operate equipment only when needed | $1,636 | $829 |
$1,697
14,583
kWh
|
$(-61.0)
-
kW-mo/yr
|
- | - | |
| 04 | 2.4133: Use most efficient type of electric motors | $33,377 | $31,490 |
$28,383
243,878
kWh
|
$4,994
-
kW-mo/yr
|
- | - | |
| 05 | 2.2621: Modify refrigeration system to operate at a lower pressure | $61,990 | $40,000 |
$53,976
463,775
kWh
|
$8,014
-
kW-mo/yr
|
- | - | |
| 06 | 2.2414: Use waste heat from hot flue gases to preheat | $19,808 | $20,000 | - | - |
$19,808
-
MMBtu
|
- | |
| 07 | 2.2511: Insulate bare equipment | $1,284 | $1,218 | - | - |
$1,284
-
MMBtu
|
- | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,669 | $10,828 |
$5,461
46,992
kWh
|
$1,208
-
kW-mo/yr
|
- | - | |
| 09 | 2.7135: Install occupancy sensors | $1,066 | $2,688 |
$685
5,882
kWh
|
$381
-
kW-mo/yr
|
- | - | |
| 10 | 3.2171: Use an automatic plate processor | $27,300 | $40,500 | - | - | - |
$27,300
-
lb
|
|
| 11 | 2.8114: Change rate schedules or other changes in utility service | $227,033 | $40,600 |
$227,033
-
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $384,226 | $188,153 |
$321,098
815,837
kWh
|
$14,736
-
kW-mo/yr
|
$21,092
-
MMBtu
|
$27,300
-
lb
|
||
| TOTAL IMPLEMENTED | $136,081 | $127,553 |
$92,961
806,033
kWh
|
$14,536
-
kW-mo/yr
|
$1,284
-
MMBtu
|
$27,300
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs