| Assessment Year | 2001 |
|---|---|
| Principal Product | Chemicals |
| NAICS |
n/a
|
| SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 32 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,500
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $35,904 | 574,400 |
kWh
|
$0.063 |
| Electricity Demand | $5,256 | 2,045 |
kW-mo/yr
|
$2.57 |
| Electricity Fees | $3,687 | - |
|
- |
| Natural Gas | $1,551 | 163 |
MMBtu
|
$9.52 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $5,228 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $738 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $800 | $1,741 |
$693
12,228
kWh
|
$107
-
kW-mo/yr
|
- | |
| 02 | 2.7124: Make a practice of turning off lights when not needed | $738 | $210 |
$451
8,006
kWh
|
$287
-
kW-mo/yr
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $539 | $1,466 |
$386
5,967
kWh
|
$153
-
kW-mo/yr
|
- | |
| 04 | 2.7135: Install occupancy sensors | $62 | $300 |
$38
930
kWh
|
$24
-
kW-mo/yr
|
- | |
| 05 | 2.7232: Replace existing hvac unit with high efficiency model | $1,049 | $750 |
$971
17,232
kWh
|
$78
-
kW-mo/yr
|
- | |
| 06 | 3.6192: Use a less expensive method of waste removal | $2,040 | $60 | - | - | $2,040 | |
| TOTAL RECOMMENDED | $5,228 | $4,527 |
$2,539
44,363
kWh
|
$649
-
kW-mo/yr
|
$2,040 | ||
| TOTAL IMPLEMENTED | $738 | $210 |
$451
8,006
kWh
|
$287
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs