Assessment Year | 2004 |
---|---|
Principal Product | Chocolate Product |
NAICS | 311351: Chocolate and Confectionery Manufacturing from Cacao Beans |
SIC | 2066: Chocolate and Cocoa Products |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
120,000
ft2
|
Annual Production | 0
lb
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $598,829 | 5,317,200 |
kWh
|
$0.11 |
Electricity Demand | $158,948 | 12,496 |
kW-mo/yr
|
$12.72 |
Natural Gas | $65,612 | 8,170 |
MMBtu
|
$8.03 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $99,214 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $57,941 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $14,198 | - |
$14,198
126,072
kWh
|
- | - | - | |
02 | 2.2111: Install steam trap | $1,304 | $299 |
$1,104
9,804
kWh
|
$200
-
kW-mo/yr
|
- | - | |
03 | 2.4133: Use most efficient type of electric motors | $7,053 | $2,417 |
$5,919
52,564
kWh
|
$1,134
-
kW-mo/yr
|
- | - | |
04 | 2.7135: Install occupancy sensors | $2,015 | $1,440 |
$1,752
15,557
kWh
|
$263
-
kW-mo/yr
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,516 | $14,960 |
$8,905
79,073
kWh
|
$1,611
-
kW-mo/yr
|
- | - | |
06 | 2.6231: Utilize controls to operate equipment only when needed | $272 | $571 |
$216
1,920
kWh
|
$56
-
kW-mo/yr
|
- | - | |
07 | 2.7135: Install occupancy sensors | $442 | $1,200 |
$274
2,433
kWh
|
$168
-
kW-mo/yr
|
- | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,037 | $5,155 |
$1,868
16,548
kWh
|
$169
-
kW-mo/yr
|
- | - | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,517 | $8,685 |
$2,135
18,960
kWh
|
$382
-
kW-mo/yr
|
- | - | |
10 | 3.2111: Install redundant equipment to avoid losses caused by equipment failure and routine maintenance | $34,944 | $72 | - | - | - |
$34,944
-
lb
|
|
11 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $20,271 | $21,650 | - | - | - |
$20,271
-
lb
|
|
12 | 2.3212: Optimize plant power factor | $3,645 | $2,914 | - | - | $3,645 | - | |
TOTAL RECOMMENDED | $99,214 | $59,363 |
$36,371
322,931
kWh
|
$3,983
-
kW-mo/yr
|
$3,645 |
$55,215
-
lb
|
||
TOTAL IMPLEMENTED | $57,941 | $3,988 |
$21,495
190,873
kWh
|
$1,502
-
kW-mo/yr
|
- |
$34,944
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs