Assessment Year | 2003 |
---|---|
Principal Product | Almonds products |
NAICS | 311911: Roasted Nuts and Peanut Butter Manufacturing |
SIC | 2068: Salted and Roasted Nuts and Seeds |
Sales Range | n/a |
# of Employees | 600 |
Plant Area |
1,400,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,049,439 | 26,961,990 |
kWh
|
$0.039 |
Electricity Demand | $473,224 | 63,626 |
kW-mo/yr
|
$7.44 |
Natural Gas | $418,865 | 55,849 |
MMBtu
|
$7.50 |
LPG | $388,000 | 141,091 |
MMBtu
|
$2.75 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $257,198 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $37,839 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2135: Repair and eliminate steam leaks | $1,765 | $300 | - | - |
$1,765
-
MMBtu
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,656 | $480 |
$1,656
54,885
kWh
|
- | - | - | - | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $16,380 | $8,846 |
$12,980
333,500
kWh
|
$3,400
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.2621: Modify refrigeration system to operate at a lower pressure | $106,094 | $76,555 |
$84,074
2,160,201
kWh
|
$22,020
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $11,201 | $7,700 |
$9,901
254,386
kWh
|
$1,300
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $728 | $728 |
$484
12,788
kWh
|
$244
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $946 | $1,286 |
$684
17,568
kWh
|
$262
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.1233: Analyze flue gas for proper air/fuel ratio | $36,828 | $60,000 | - | - |
$36,828
-
MMBtu
|
- | - | - | |
09 | 2.7226: Use computer programs to optimize hvac performance | $5,493 | $15,750 |
$2,160
55,502
kWh
|
$3,333
-
kW-mo/yr
|
- | - | - | - | |
10 | 2.4133: Use most efficient type of electric motors | $6,103 | $13,336 |
$3,559
91,447
kWh
|
$2,544
-
kW-mo/yr
|
- | - | - | - | |
11 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,386 | $1,395 |
$984
25,272
kWh
|
$402
-
kW-mo/yr
|
- | - | - | - | |
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $24,355 | $84,428 |
$16,798
431,599
kWh
|
$7,557
-
kW-mo/yr
|
- | - | - | - | |
13 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $26,475 | $72,000 |
$18,797
482,976
kWh
|
$7,678
-
kW-mo/yr
|
- | - | - | - | |
14 | 2.7135: Install occupancy sensors | $3,232 | $17,400 |
$2,490
63,974
kWh
|
$742
-
kW-mo/yr
|
- | - | - | - | |
15 | 3.6192: Use a less expensive method of waste removal | $810 | - | - | - | - |
$810
-
gal
|
- | - | |
16 | 3.6112: Use filter and drying oven to reduce sludge volume | $7,467 | $6,400 | - | - | - | - |
$7,467
-
lb
|
- | |
17 | 3.6126: Direct waste gasses to boiler combustion air | $6,279 | $6,714 | - | - | - | - | - | $6,279 | |
TOTAL RECOMMENDED | $257,198 | $373,318 |
$154,567
3,984,098
kWh
|
$49,482
-
kW-mo/yr
|
$38,593
-
MMBtu
|
$810
-
gal
|
$7,467
-
lb
|
$6,279 | ||
TOTAL IMPLEMENTED | $37,839 | $116,672 |
$24,987
654,693
kWh
|
$11,087
-
kW-mo/yr
|
$1,765
-
MMBtu
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs