ITAC Assessment: SF0273
ITAC logo
ITAC Assessment: SF0273
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Almonds products
NAICS 311911: Roasted Nuts and Peanut Butter Manufacturing
SIC 2068: Salted and Roasted Nuts and Seeds
Sales Range n/a
# of Employees 600
Plant Area 1,400,000
ft2
Annual Production 0
units
Production Hrs. Annual 6,000
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,049,439 26,961,990
kWh
Electricity Demand $473,224 63,626
kW-mo/yr
Natural Gas $418,865 55,849
MMBtu
LPG $388,000 141,091
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $257,198 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $37,839

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.2135: Repair and eliminate steam leaks $1,765 $300 - - $1,765
-
MMBtu
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,656 $480 $1,656
54,885
kWh
- - - - -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $16,380 $8,846 $12,980
333,500
kWh
$3,400
-
kW-mo/yr
- - - -
04 2.2621: Modify refrigeration system to operate at a lower pressure $106,094 $76,555 $84,074
2,160,201
kWh
$22,020
-
kW-mo/yr
- - - -
05 2.4231: Reduce the pressure of compressed air to the minimum required $11,201 $7,700 $9,901
254,386
kWh
$1,300
-
kW-mo/yr
- - - -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $728 $728 $484
12,788
kWh
$244
-
kW-mo/yr
- - - -
07 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $946 $1,286 $684
17,568
kWh
$262
-
kW-mo/yr
- - - -
08 2.1233: Analyze flue gas for proper air/fuel ratio $36,828 $60,000 - - $36,828
-
MMBtu
- - -
09 2.7226: Use computer programs to optimize hvac performance $5,493 $15,750 $2,160
55,502
kWh
$3,333
-
kW-mo/yr
- - - -
10 2.4133: Use most efficient type of electric motors $6,103 $13,336 $3,559
91,447
kWh
$2,544
-
kW-mo/yr
- - - -
11 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,386 $1,395 $984
25,272
kWh
$402
-
kW-mo/yr
- - - -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $24,355 $84,428 $16,798
431,599
kWh
$7,557
-
kW-mo/yr
- - - -
13 2.1311: Replace electrically-operated equipment with fossil fuel equipment $26,475 $72,000 $18,797
482,976
kWh
$7,678
-
kW-mo/yr
- - - -
14 2.7135: Install occupancy sensors $3,232 $17,400 $2,490
63,974
kWh
$742
-
kW-mo/yr
- - - -
15 3.6192: Use a less expensive method of waste removal $810 - - - - $810
-
gal
- -
16 3.6112: Use filter and drying oven to reduce sludge volume $7,467 $6,400 - - - - $7,467
-
lb
-
17 3.6126: Direct waste gasses to boiler combustion air $6,279 $6,714 - - - - - $6,279
TOTAL RECOMMENDED $257,198 $373,318 $154,567
3,984,098
kWh
$49,482
-
kW-mo/yr
$38,593
-
MMBtu
$810
-
gal
$7,467
-
lb
$6,279
TOTAL IMPLEMENTED $37,839 $116,672 $24,987
654,693
kWh
$11,087
-
kW-mo/yr
$1,765
-
MMBtu
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs