ITAC Assessment: SF0261
ITAC logo
ITAC Assessment: SF0261
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Automotive Seating, Headliner
NAICS 336360: Motor Vehicle Seating and Interior Trim Manufacturing
SIC 2531: Public Building and Related Furniture
Sales Range $100
M
to 500
M
# of Employees 325
Plant Area 106,000
ft2
Annual Production 61,440
pieces
Production Hrs. Annual 6,240
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $514,148 17,475
kWh
Electricity Demand $133,385 10,570
kW-mo/yr
Natural Gas $6,627 994
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $133,415 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $35,479

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
01 2.2135: Repair and eliminate steam leaks $10,012 - $8,063
74,155
kWh
$1,949
-
kW-mo/yr
-
02 2.4224: Upgrade controls on compressors $3,924 $52 $3,291
14,994
kWh
$633
-
kW-mo/yr
-
03 2.7135: Install occupancy sensors $4,341 $485 $3,496
34,819
kWh
$845
-
kW-mo/yr
-
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $26,010 $33,679 $20,948
208,637
kWh
$5,062
-
kW-mo/yr
-
05 3.6123: Burn wood by-products for heat $25,467 $4,500 - - $25,467
-
lb
06 3.5212: Regrind, reuse, or sell scrap plastic parts $63,661 $36,750 - - $63,661
-
lb
TOTAL RECOMMENDED $133,415 $75,466 $35,798
332,605
kWh
$8,489
-
kW-mo/yr
$89,128
-
lb
TOTAL IMPLEMENTED $35,479 $4,500 $8,063
74,155
kWh
$1,949
-
kW-mo/yr
$25,467
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs