Assessment Year | 2003 |
---|---|
Principal Product | Newspaper |
NAICS | 511110: Newspaper Publishers |
SIC | 2711: Newspapers: Publishing, or Publishing and Printing |
Sales Range | $50 M to 100M |
# of Employees | 625 |
Plant Area |
156,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 3,328
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $185,845 | 5,065,104 |
kWh
|
$0.037 |
Electricity Demand | $96,904 | 11,094 |
kW-mo/yr
|
$8.73 |
Natural Gas | $22,528 | 3,608 |
MMBtu
|
$6.24 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $43,401 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,807 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,228 | $140 |
$878
23,919
kWh
|
$350
-
kW-mo/yr
|
- | |
02 | 2.4239: Eliminate or reduce compressed air usage | $9,649 | $3,715 |
$5,192
141,513
kWh
|
$4,457
-
kW-mo/yr
|
- | |
03 | 2.2612: Use cooling tower water instead of refrigeration | $7,212 | $5,250 |
$5,866
159,896
kWh
|
$1,346
-
kW-mo/yr
|
- | |
04 | 2.4226: Use / purchase optimum sized compressor | $2,226 | $3,400 |
$2,226
60,650
kWh
|
- | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,416 | $13,464 |
$3,471
94,607
kWh
|
$2,945
-
kW-mo/yr
|
- | |
06 | 2.7135: Install occupancy sensors | $3,302 | $7,220 |
$1,972
53,761
kWh
|
$1,330
-
kW-mo/yr
|
- | |
07 | 2.4133: Use most efficient type of electric motors | $353 | $796 |
$252
6,871
kWh
|
$101
-
kW-mo/yr
|
- | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,337 | $587 |
$9,295
253,328
kWh
|
$3,042
-
kW-mo/yr
|
- | |
09 | 2.3212: Optimize plant power factor | $678 | $1,749 | - |
$215
-
kW-mo/yr
|
$463 | |
TOTAL RECOMMENDED | $43,401 | $36,321 |
$29,152
794,545
kWh
|
$13,786
-
kW-mo/yr
|
$463 | ||
TOTAL IMPLEMENTED | $3,807 | $4,336 |
$3,356
91,440
kWh
|
$451
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs