Assessment Year | 2002 |
---|---|
Principal Product | Rubber Flooring |
NAICS |
n/a
|
SIC | 3061: Molded, Extruded, and Lathe-Cut Mechanical Rubber Goods |
Sales Range | $50 M to 100M |
# of Employees | 230 |
Plant Area |
120,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,250
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $546,852 | 5,248,140 |
kWh
|
$0.10 |
Electricity Demand | $175,474 | 17,509 |
kW-mo/yr
|
$10.02 |
Natural Gas | $124,478 | 29,289 |
MMBtu
|
$4.25 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $186,293 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,092 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $7,917 | $7,200 | - | - |
$7,917
-
MMBtu
|
- | - | |
02 | 2.7132: Install timers on light switches in little used areas | $3,065 | $4,060 |
$3,065
29,415
kWh
|
- | - | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $2,576 | $4,115 |
$2,576
18,948
kWh
|
- | - | - | - | |
04 | 2.4226: Use / purchase optimum sized compressor | $8,585 | $20,725 |
$8,585
71,431
kWh
|
- | - | - | - | |
05 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $19,484 | $97,649 |
$19,484
152,021
kWh
|
- | - | - | - | |
06 | 3.6192: Use a less expensive method of waste removal | $2,738 | $6,972 | - | - | - |
$2,738
-
lb
|
- | |
07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,193 | - | - | $5,193 | - | - | - | |
08 | 2.8114: Change rate schedules or other changes in utility service | $74,335 | $160,000 | - | $74,335 | - | - | - | |
09 | 4.441: Install automatic packing equipment | $62,400 | $250,000 | - | - | - | - | $62,400 | |
TOTAL RECOMMENDED | $186,293 | $550,721 |
$33,710
271,815
kWh
|
$79,528 |
$7,917
-
MMBtu
|
$2,738
-
lb
|
$62,400 | ||
TOTAL IMPLEMENTED | $19,092 | $31,812 |
$11,161
90,379
kWh
|
$5,193 | - |
$2,738
-
lb
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs