ITAC Assessment: SF0245
ITAC logo
ITAC Assessment: SF0245
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Rubber Flooring
NAICS
n/a
SIC 3061: Molded, Extruded, and Lathe-Cut Mechanical Rubber Goods
Sales Range $50
M
to 100
M
# of Employees 230
Plant Area 120,000
ft2
Annual Production 0
units
Production Hrs. Annual 4,250
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $546,852 5,248,140
kWh
Electricity Demand $175,474 17,509
kW-mo/yr
Natural Gas $124,478 29,289
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $186,293 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,092

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $7,917 $7,200 - - $7,917
-
MMBtu
- -
02 2.7132: Install timers on light switches in little used areas $3,065 $4,060 $3,065
29,415
kWh
- - - -
03 2.4133: Use most efficient type of electric motors $2,576 $4,115 $2,576
18,948
kWh
- - - -
04 2.4226: Use / purchase optimum sized compressor $8,585 $20,725 $8,585
71,431
kWh
- - - -
05 2.7491: Insulate glazing, walls, ceilings, and roofs $19,484 $97,649 $19,484
152,021
kWh
- - - -
06 3.6192: Use a less expensive method of waste removal $2,738 $6,972 - - - $2,738
-
lb
-
07 2.3131: Reschedule plant operations or reduce load to avoid peaks $5,193 - - $5,193 - - -
08 2.8114: Change rate schedules or other changes in utility service $74,335 $160,000 - $74,335 - - -
09 4.441: Install automatic packing equipment $62,400 $250,000 - - - - $62,400
TOTAL RECOMMENDED $186,293 $550,721 $33,710
271,815
kWh
$79,528 $7,917
-
MMBtu
$2,738
-
lb
$62,400
TOTAL IMPLEMENTED $19,092 $31,812 $11,161
90,379
kWh
$5,193 - $2,738
-
lb
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs