Assessment Year | 2002 |
---|---|
Principal Product | Automotive Rubber Seals |
NAICS |
n/a
|
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 180 |
Plant Area |
54,700
ft2
|
Annual Production | 4,500,000
pieces
|
Production Hrs. Annual | 4,454
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $197,985 | 2,135,058 |
kWh
|
$0.093 |
Electricity Demand | $68,087 | 5,564 |
kW-mo/yr
|
$12.24 |
Natural Gas | $13,200 | 1,640 |
MMBtu
|
$8.05 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $66,748 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,590 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,590 | - |
$2,590
16,398
kWh
|
- | |
02 | 2.4223: Install direct acting units in place of compressed air pressure system in safety system | $1,388 | $380 |
$1,388
10,446
kWh
|
- | |
03 | 2.7132: Install timers on light switches in little used areas | $2,551 | $1,000 |
$2,551
14,752
kWh
|
- | |
04 | 2.4133: Use most efficient type of electric motors | $1,747 | $777 |
$1,747
10,114
kWh
|
- | |
05 | 2.7135: Install occupancy sensors | $238 | $120 |
$238
1,379
kWh
|
- | |
06 | 2.4224: Upgrade controls on compressors | $1,694 | $1,002 |
$1,694
9,414
kWh
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,515 | $11,595 |
$5,515
30,637
kWh
|
- | |
08 | 2.5123: Reduce fluid flow rates | $19,758 | $50,798 |
$19,758
96,121
kWh
|
- | |
09 | 3.5217: Reuse / recycle/ sell paper products | $10,700 | $8,117 | - |
$10,700
-
lb
|
|
10 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $20,567 | $16,445 | - |
$20,567
-
lb
|
|
TOTAL RECOMMENDED | $66,748 | $90,234 |
$35,481
189,261
kWh
|
$31,267
-
lb
|
||
TOTAL IMPLEMENTED | $2,590 | - |
$2,590
16,398
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs