ITAC Assessment: UD1098
ITAC logo
ITAC Assessment: UD1098
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Injection Molded and Extruded Plastic Components for Motor Vehicles
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $100
M
to 500
M
# of Employees 150
Plant Area 125,000
ft2
Annual Production 1,020,865
units
Production Hrs. Annual 6,420
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $256,634 3,348,063
kWh
Electricity Demand $42,979 8,595
kW-mo/yr
Electricity Fees $5,654 -
Natural Gas $6,589 794
MMBtu
Waste Disposal Costs
Water Usage $1,248 186
Tgal
Water Disposal $960 186
Tgal
Other Liquid (non-haz) $126 1
gal
TOTAL YEARLY COSTS $314,190
RECOMMENDED SAVINGS* $33,190 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.2511: Insulate bare equipment $5,147 $1,610 $4,574
59,637
kWh
$573
-
kW-mo/yr
- - -
02 2.7243: Improve air circulation with destratification fans / other methods $15,813 $5,000 $12,542
163,522
kWh
$3,271
-
kW-mo/yr
- - -
03 2.7313: Recycle air for heating, ventilation and air conditioning $6,529 $7,106 $4,552
59,354
kWh
- $1,977
-
MMBtu
- -
04 2.7241: Install outside air damper / economizer on hvac unit $2,612 $306 $2,612
34,058
kWh
- - - -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,550 $1,184 $1,550
20,205
kWh
- - - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $715 $1,235 $635
8,276
kWh
$80
-
kW-mo/yr
- - -
07 2.4231: Reduce the pressure of compressed air to the minimum required $513 - $456
5,942
kWh
$57
-
kW-mo/yr
- - -
08 2.7135: Install occupancy sensors $311 $509 $235
3,058
kWh
$25
-
kW-mo/yr
- $39 $12
TOTAL RECOMMENDED $33,190 $16,950 $27,156
354,052
kWh
$4,006
-
kW-mo/yr
$1,977
-
MMBtu
$39 $12
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs