Assessment Year | 2001 |
---|---|
Principal Product | mattresses and box springs |
NAICS |
n/a
|
SIC | 2515: Mattresses, Foundations, and Convertible Beds |
Sales Range | $50 M to 100M |
# of Employees | 160 |
Plant Area |
238,000
ft2
|
Annual Production | 350,000
units
|
Production Hrs. Annual | 4,550
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $106,041 | 920,400 |
kWh
|
$0.12 |
Natural Gas | $127 | 12 |
MMBtu
|
$10.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $20,754 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,089 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 3.7392: Apply a protective coating to racks and tanks | $2,925 | - |
$2,925
20,519
kWh
|
|
02 | 2.4221: Install compressor air intakes in coolest locations | $1,216 | $112 |
$1,216
8,537
kWh
|
|
03 | 2.4239: Eliminate or reduce compressed air usage | $3,948 | $2,195 |
$3,948
27,708
kWh
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,618 | $4,030 |
$3,618
25,389
kWh
|
|
05 | 2.7135: Install occupancy sensors | $7,920 | $14,210 |
$7,920
55,583
kWh
|
|
06 | 2.7132: Install timers on light switches in little used areas | $897 | $2,040 |
$897
6,297
kWh
|
|
07 | 4.111: Add equipment/ operators to reduce production bottleneck | $230 | $618 |
$230
1,613
kWh
|
|
TOTAL RECOMMENDED | $20,754 | $23,205 |
$20,754
145,646
kWh
|
||
TOTAL IMPLEMENTED | $8,089 | $2,307 |
$8,089
56,764
kWh
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs