Assessment Year | 2001 |
---|---|
Principal Product | Unit Dose inhalation solution |
NAICS |
n/a
|
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $100 M to 500M |
# of Employees | 869 |
Plant Area |
345,000
ft2
|
Annual Production | 677,000,000
units
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,264,926 | 14,860,503 |
kWh
|
$0.085 |
Natural Gas | $246,694 | 39,282 |
MMBtu
|
$6.28 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $489,326 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $9,345 | $540 | n/a |
$9,345
112,455
kWh
|
- | - |
02 | 2.1231: Establish burner maintenance schedule for boilers | $1,556 | - | n/a | - |
$1,556
-
MMBtu
|
- |
03 | 2.2153: Close off unneeded steam lines | $2,618 | $172 | n/a |
$2,618
20,228
kWh
|
- | - |
04 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $18,526 | $4,994 | n/a |
$18,526
143,170
kWh
|
- | - |
05 | 2.7132: Install timers on light switches in little used areas | $10,562 | $3,240 | n/a |
$10,562
81,625
kWh
|
- | - |
06 | 2.4221: Install compressor air intakes in coolest locations | $6,146 | $2,800 | n/a |
$6,146
47,496
kWh
|
- | - |
07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $25,962 | $13,200 | n/a | - |
$25,962
-
MMBtu
|
- |
08 | 2.7132: Install timers on light switches in little used areas | $11,660 | $9,500 | n/a |
$11,660
90,105
kWh
|
- | - |
09 | 2.4133: Use most efficient type of electric motors | $6,142 | $6,113 | n/a |
$6,142
86,512
kWh
|
- | - |
10 | 4.111: Add equipment/ operators to reduce production bottleneck | $259,156 | $256,500 | n/a |
$259,156
10,546,893
kWh
|
- | - |
11 | 2.7135: Install occupancy sensors | $17,495 | $33,556 | n/a |
$17,495
282,373
kWh
|
- | - |
12 | 2.3212: Optimize plant power factor | $120,158 | $160,000 | n/a | - | - | $120,158 |
TOTAL RECOMMENDED | $489,326 | $490,615 |
$341,650
11,410,857
kWh
|
$27,518
-
MMBtu
|
$120,158 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs