ITAC Assessment: SF0221
ITAC logo
ITAC Assessment: SF0221
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Plastic Molding
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 100
Plant Area 83,000
ft2
Annual Production 350
ton
Production Hrs. Annual 6,240
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $294,544 2,754,626
kWh
Natural Gas $5,373 507
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $74,282 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,051

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Other Liquid (non-haz) Savings
01 2.6218: Turn off equipment when not in use $185 - $185
1,521
kWh
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,977 $480 $4,977
44,803
kWh
-
03 2.4224: Upgrade controls on compressors $2,046 $344 $2,046
16,801
kWh
-
04 2.2612: Use cooling tower water instead of refrigeration $2,217 $495 $2,217
18,204
kWh
-
05 2.7135: Install occupancy sensors $1,099 $840 $1,099
9,023
kWh
-
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,141 $7,697 $7,141
58,632
kWh
-
07 2.4231: Reduce the pressure of compressed air to the minimum required $1,570 $2,262 $1,570
12,890
kWh
-
08 2.1121: Use insulation in furnaces to facilitate heating / cooling $1,259 $1,259 $1,259
50,657
kWh
-
09 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $53,204 $139,820 $53,204
436,815
kWh
-
10 3.5217: Reuse / recycle/ sell paper products $584 $80 - $584
-
gal
TOTAL RECOMMENDED $74,282 $153,277 $73,698
649,346
kWh
$584
-
gal
TOTAL IMPLEMENTED $9,051 $2,163 $8,467
113,782
kWh
$584
-
gal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Other Liquid (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs