ITAC Assessment: SF0214
ITAC logo
ITAC Assessment: SF0214
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Printed Circuit Boards
NAICS
n/a
SIC 3672: Printed Circuit Boards
Sales Range $50
M
to 100
M
# of Employees 340
Plant Area 50,000
ft2
Annual Production 7,500
thousand feet
Production Hrs. Annual 6,968
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $782,504 9,373,352
kWh
Natural Gas $18,188 2,425
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $64,271 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,930

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.6218: Turn off equipment when not in use $606 - $606
7,216
kWh
-
02 2.4224: Upgrade controls on compressors $3,471 $400 $3,471
41,585
kWh
-
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $864 $399 $864
10,351
kWh
-
04 2.4133: Use most efficient type of electric motors $27,587 $26,393 $27,587
330,479
kWh
-
05 2.7132: Install timers on light switches in little used areas $1,324 $2,880 $1,324
15,856
kWh
-
06 2.4321: Upgrade obsolete equipment $2,327 $4,202 $2,327
27,872
kWh
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,441 $3,971 $1,441
17,264
kWh
-
08 2.4231: Reduce the pressure of compressed air to the minimum required $1,739 $6,370 $1,739
20,832
kWh
-
09 2.1221: Replace obsolete burners with more efficient ones $24,912 $46,855 $40,385
483,773
kWh
$(-15,473.0)
-
MMBtu
TOTAL RECOMMENDED $64,271 $91,470 $79,744
955,228
kWh
$(-15,473.0)
-
MMBtu
TOTAL IMPLEMENTED $1,930 $2,880 $1,930
23,072
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs