Assessment Year | 2001 |
---|---|
Principal Product | Printed Circuit Boards |
NAICS |
n/a
|
SIC | 3672: Printed Circuit Boards |
Sales Range | $50 M to 100M |
# of Employees | 340 |
Plant Area |
50,000
ft2
|
Annual Production | 7,500
thousand feet
|
Production Hrs. Annual | 6,968
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $782,504 | 9,373,352 |
kWh
|
$0.083 |
Natural Gas | $18,188 | 2,425 |
MMBtu
|
$7.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $64,271 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,930 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $606 | - |
$606
7,216
kWh
|
- | |
02 | 2.4224: Upgrade controls on compressors | $3,471 | $400 |
$3,471
41,585
kWh
|
- | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $864 | $399 |
$864
10,351
kWh
|
- | |
04 | 2.4133: Use most efficient type of electric motors | $27,587 | $26,393 |
$27,587
330,479
kWh
|
- | |
05 | 2.7132: Install timers on light switches in little used areas | $1,324 | $2,880 |
$1,324
15,856
kWh
|
- | |
06 | 2.4321: Upgrade obsolete equipment | $2,327 | $4,202 |
$2,327
27,872
kWh
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,441 | $3,971 |
$1,441
17,264
kWh
|
- | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,739 | $6,370 |
$1,739
20,832
kWh
|
- | |
09 | 2.1221: Replace obsolete burners with more efficient ones | $24,912 | $46,855 |
$40,385
483,773
kWh
|
$(-15,473.0)
-
MMBtu
|
|
TOTAL RECOMMENDED | $64,271 | $91,470 |
$79,744
955,228
kWh
|
$(-15,473.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $1,930 | $2,880 |
$1,930
23,072
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs