| Assessment Year | 1999 |
|---|---|
| Principal Product | Printed Labels |
| NAICS |
n/a
|
| SIC | 2759: Commercial Printing, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 40 |
| Plant Area |
25,000
ft2
|
| Annual Production | 4,810
units
|
| Production Hrs. Annual | 5,590
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $65,549 | 507,620 |
kWh
|
$0.13 |
| Natural Gas | $3,078 | 454 |
MMBtu
|
$6.78 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $50,242 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,187 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $3,158 | $1,318 |
$766
6,448
kWh
|
$2,392
-
MMBtu
|
- | - | |
| 02 | 2.7135: Install occupancy sensors | $547 | $1,344 |
$547
4,689
kWh
|
- | - | - | |
| 03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,661 | $4,765 |
$2,745
23,740
kWh
|
$(-1,084.0)
-
MMBtu
|
- | - | |
| 04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $482 | $1,433 |
$641
5,569
kWh
|
$(-159.0)
-
MMBtu
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,532 | $4,900 |
$1,532
13,189
kWh
|
- | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,403 | $12,245 |
$3,403
29,308
kWh
|
- | - | - | |
| 07 | 3.8141: Regenerate cleaning solvent on-site and reuse | $17,794 | $14,320 |
$(-351.0)
(-2,931)
kWh
|
- |
$18,145
-
lb
|
- | |
| 08 | 4.652: Replace existing equipment with more suitable substitutes | $21,665 | $272,034 | - | - | - | $21,665 | |
| TOTAL RECOMMENDED | $50,242 | $312,359 |
$9,283
80,012
kWh
|
$1,149
-
MMBtu
|
$18,145
-
lb
|
$21,665 | ||
| TOTAL IMPLEMENTED | $4,187 | $4,095 |
$1,954
16,706
kWh
|
$2,233
-
MMBtu
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs