ITAC Assessment: SF0164
ITAC logo
ITAC Assessment: SF0164
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Packaging Foam
NAICS
n/a
SIC 3086: Plastics Foam Products
Sales Range $5
M
to 10
M
# of Employees 55
Plant Area 90,000
ft2
Annual Production 1,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $150,578 2,589,390
kWh
Electricity Demand $73,592 5,866
kW-mo/yr
Natural Gas $215,420 64,487
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $44,275 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,886 $1,618 $4,886
84,115
kWh
- - - -
02 2.2135: Repair and eliminate steam leaks $278 $125 - - $278
-
MMBtu
- -
03 2.7135: Install occupancy sensors $1,460 $896 $1,020
17,585
kWh
$440
-
kW-mo/yr
- - -
04 2.4133: Use most efficient type of electric motors $1,384 $981 $967
16,706
kWh
$417
-
kW-mo/yr
- - -
05 2.4322: Use or replace with energy efficient substitutes $6,137 $4,800 $4,292
73,857
kWh
$1,845
-
kW-mo/yr
- - -
06 2.4221: Install compressor air intakes in coolest locations $1,717 $2,424 $1,169
20,223
kWh
$548
-
kW-mo/yr
- - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,244 $4,080 $805
13,775
kWh
$439
-
kW-mo/yr
- - -
08 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $1,899 $6,500 $1,146
19,637
kWh
$753
-
kW-mo/yr
- - -
09 2.2449: Recover heat from exhausted steam, hot air or hot water $631 $2,500 - - $631
-
MMBtu
- -
10 3.5314: Use in-process recycling whenever possible $2,233 - - - - - $2,233
-
lb
11 3.5316: Contract a wood pallet recycling company $6,780 $8,175 - - - - $6,780
-
lb
12 3.4111: Use closed cycle process to minimize waste water production $994 $371 $(-128.0)
(-1,465)
kWh
- - $1,122
-
Tgal
-
13 2.3321: Use steam pressure reduction to generate power $14,632 $53,728 $10,234
527,550
kWh
$4,398
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $44,275 $86,198 $24,391
771,983
kWh
$8,840
-
kW-mo/yr
$909
-
MMBtu
$1,122
-
Tgal
$9,013
-
lb
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs