Assessment Year | 1998 |
---|---|
Principal Product | Printed Circuit Boards |
NAICS |
n/a
|
SIC | 3672: Printed Circuit Boards |
Sales Range | $50 M to 100M |
# of Employees | 95 |
Plant Area |
39,000
ft2
|
Annual Production | 200,000
pieces
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $49,627 | 721,864 |
kWh
|
$0.069 |
Electricity Demand | $11,961 | 2,318 |
kW-mo/yr
|
$5.16 |
Natural Gas | $1,708 | 212 |
MMBtu
|
$8.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $207,197 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $203,685 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $690 | $15 |
$644
9,379
kWh
|
$46
-
kW-mo/yr
|
- | - | |
02 | 2.6218: Turn off equipment when not in use | $368 | - |
$368
5,275
kWh
|
- | - | - | |
03 | 2.6231: Utilize controls to operate equipment only when needed | $555 | $495 |
$457
6,741
kWh
|
$98
-
kW-mo/yr
|
- | - | |
04 | 2.7135: Install occupancy sensors | $844 | $2,640 |
$643
9,379
kWh
|
$201
-
kW-mo/yr
|
- | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,333 | $5,522 |
$936
13,482
kWh
|
$397
-
kW-mo/yr
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,627 | $25,680 |
$4,544
66,237
kWh
|
$1,083
-
kW-mo/yr
|
- | - | |
07 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $780 | $145 | - | - |
$780
-
lb
|
- | |
08 | 4.126: Install sensors to detect defects | $80,000 | $40,000 | - | - | - | $80,000 | |
09 | 4.112: Replace old machine with new automatic multi-station tool | $117,000 | $400,000 | - | - | - | $117,000 | |
TOTAL RECOMMENDED | $207,197 | $474,497 |
$7,592
110,493
kWh
|
$1,825
-
kW-mo/yr
|
$780
-
lb
|
$197,000 | ||
TOTAL IMPLEMENTED | $203,685 | $465,695 |
$5,556
80,891
kWh
|
$1,129
-
kW-mo/yr
|
- | $197,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs