Assessment Year | 1998 |
---|---|
Principal Product | Buses |
NAICS |
n/a
|
SIC | 3711: Motor Vehicles and Passenger Car Bodies |
Sales Range | $100 M to 500M |
# of Employees | 450 |
Plant Area |
130,000
ft2
|
Annual Production | 1,000
pieces
|
Production Hrs. Annual | 6,684
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $177,714 | 2,963,951 |
kWh
|
$0.060 |
Electricity Demand | $98,138 | 7,622 |
kW-mo/yr
|
$12.88 |
Natural Gas | $119,782 | 24,151 |
MMBtu
|
$4.96 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $415,308 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $33,438 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4154: Avoid rewinding motors more than twice | $1,032 | $817 |
$707
4,982
kWh
|
$325
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
02 | 2.7144: Install spectral reflectors / delamp | $1,629 | $1,694 |
$1,068
19,343
kWh
|
$561
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $6,511 | $8,195 |
$6,916
115,182
kWh
|
$2,035
-
kW-mo/yr
|
$(-2,440.0)
-
MMBtu
|
- | - | - | - | - | - | |
04 | 2.7134: Use photocell controls | $3,137 | $5,250 |
$2,007
33,411
kWh
|
$1,130
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $30,063 | - | - | - | - | - |
$30,063
-
lb
|
- | - | - | - | |
06 | 3.5313: Increase amount of waste recovered for resale | $2,343 | - | - | - | - | - |
$2,343
-
lb
|
- | - | - | - | |
07 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $21,615 | $8,445 | - | - | - | - |
$21,615
-
lb
|
- | - | - | - | |
08 | 3.5314: Use in-process recycling whenever possible | $42,174 | $120,374 | - | - | - | - |
$29,700
-
lb
|
- | $12,474 | - | - | |
09 | 3.2124: Convert to air assisted / airless paint guns | $227,825 | $1,214 | - | - | - | - | - | - | $33,569 | $194,256 | - | |
10 | 3.1191: Change procedures / equipment / operating conditions | $5,903 | $70 | - | - | - | - | - |
$3,095
-
lb
|
$2,808 | - | - | |
11 | 3.2124: Convert to air assisted / airless paint guns | $73,076 | $5,598 | - | - | - |
$2,129
-
gal
|
- | - | $7,584 | - | $63,363 | |
TOTAL RECOMMENDED | $415,308 | $151,657 |
$10,698
172,918
kWh
|
$4,051
-
kW-mo/yr
|
$(-2,440.0)
-
MMBtu
|
$2,129
-
gal
|
$83,721
-
lb
|
$3,095
-
lb
|
$56,435 | $194,256 | $63,363 | ||
TOTAL IMPLEMENTED | $33,438 | $817 |
$707
4,982
kWh
|
$325
-
kW-mo/yr
|
- | - |
$32,406
-
lb
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs