ITAC Assessment: SF0145
ITAC logo
ITAC Assessment: SF0145
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Canned Vegetables and Fruits
NAICS
n/a
SIC 2030:
Sales Range $10
M
to 50
M
# of Employees 260
Plant Area 375,000
ft2
Annual Production 110,000,000
lb
Production Hrs. Annual 4,800
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $250,452 8,778,136
kWh
Electricity Demand $140,514 16,651
kW-mo/yr
Natural Gas $102,911 36,754
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $174,532 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $63,773

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas $1,575 - $1,575
48,945
kWh
- - - - - -
02 2.3132: Recharge batteries on during off-peak demand periods $6,958 - - - $6,958 - - - -
03 2.2135: Repair and eliminate steam leaks $2,548 $600 - - - $2,548
-
MMBtu
- - -
04 2.4239: Eliminate or reduce compressed air usage $382 $150 $257
7,620
kWh
$125
-
kW-mo/yr
- - - - -
05 2.7135: Install occupancy sensors $2,965 $4,440 $1,935
56,565
kWh
$1,030
-
kW-mo/yr
- - - - -
06 2.4133: Use most efficient type of electric motors $2,334 $3,981 $1,318
38,394
kWh
$1,016
-
kW-mo/yr
- - - - -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,553 $11,064 $1,773
51,876
kWh
$1,024
-
kW-mo/yr
- - $756
-
Tgal
- -
08 2.7134: Use photocell controls $7,051 $27,750 $4,722
137,749
kWh
$2,329
-
kW-mo/yr
- - - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $5,405 $21,900 $3,448
100,821
kWh
$1,957
-
kW-mo/yr
- - - - -
10 3.5313: Increase amount of waste recovered for resale $7,480 $550 - - - - - $7,480
-
lb
-
11 3.4155: Meter waste water $91,785 $180,000 - - - - $91,785
-
Tgal
- -
12 4.214: Purchase appropriately sized material $39,680 $15,000 - - - - - - $39,680
13 4.446: Automate finishing process $2,816 $5,000 - - - - - - $2,816
TOTAL RECOMMENDED $174,532 $270,435 $15,028
441,970
kWh
$7,481
-
kW-mo/yr
$6,958 $2,548
-
MMBtu
$92,541
-
Tgal
$7,480
-
lb
$42,496
TOTAL IMPLEMENTED $63,773 $25,281 $3,150
94,959
kWh
$1,141
-
kW-mo/yr
$6,958 $2,548
-
MMBtu
- $7,480
-
lb
$42,496
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs