| Assessment Year | 1994 |
|---|---|
| Principal Product | Underground Utility Vaults |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 80 |
| Plant Area |
260,000
ft2
|
| Annual Production | 112,000
pieces
|
| Production Hrs. Annual | 2,040
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $64,203 | 544,256 |
kWh
|
$0.12 |
| Natural Gas | $296 | 19 |
MMBtu
|
$15.58 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $19,275 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,759 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,307 | $5,375 |
$5,307
44,842
kWh
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,306 | $900 |
$5,306
44,842
kWh
|
- | |
| 03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $5,035 | $5,600 |
$6,743
57,151
kWh
|
$(-1,708.0)
-
MMBtu
|
|
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,511 | $2,628 |
$1,511
12,896
kWh
|
- | |
| 05 | 2.6231: Utilize controls to operate equipment only when needed | $1,174 | $832 |
$1,174
9,965
kWh
|
- | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $194 | $223 |
$194
1,758
kWh
|
- | |
| 07 | 2.4133: Use most efficient type of electric motors | $748 | $837 |
$748
6,448
kWh
|
- | |
| TOTAL RECOMMENDED | $19,275 | $16,395 |
$20,983
177,902
kWh
|
$(-1,708.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $7,759 | $4,588 |
$7,759
65,944
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs