| Assessment Year | 2026 |
|---|---|
| Principal Product | Aerospace metal parts |
| NAICS | 336412: Aircraft Engine and Engine Parts Manufacturing |
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 150 |
| Plant Area |
400,000
ft2
|
| Annual Production | 1,000,000
units
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $1,026,637 | 5,467,289 |
kWh
|
$0.19 | |
| Electricity Demand | $1,098,118 | 14,820 |
kW-mo/yr
|
$74.10 | |
| Electricity Fees | $18,304 | - |
|
- | |
| Natural Gas | $39,050 | 3,836 |
MMBtu
|
$10.18 | |
| Waste Disposal Costs | |||||
| Other Liquid (non-haz) | $144,000 | 36,000 |
gal
|
$4.00 | |
| TOTAL YEARLY COSTS | $2,326,109 | ||||
| RECOMMENDED SAVINGS* | $987,708 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $343,390 | $403,026 |
$129,982
692,131
kWh
|
$213,408
-
kW-mo/yr
|
- | |
| 02 | 2.3141: Use battery storage for demand control | $331,268 | $168,800 |
$(-6,628.2)
(-35,294)
kWh
|
$337,896
-
kW-mo/yr
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $377 | $169 |
$177
943
kWh
|
$200
-
kW-mo/yr
|
- | |
| 04 | 2.4223: Install direct acting units in place of compressed air pressure system in safety system | $48,628 | $48,200 |
$48,628
258,935
kWh
|
- | - | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $50,834 | $15,400 |
$28,412
151,288
kWh
|
$22,422
-
kW-mo/yr
|
- | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $13,051 | $7,036 |
$5,062
26,954
kWh
|
$7,989
-
kW-mo/yr
|
- | |
| 07 | 4.212: Adopt in-house material generation | $141,736 | $464,200 |
$(-2,263.5)
(-12,053)
kWh
|
- |
$144,000
-
gal
|
|
| 08 | 2.4133: Use most efficient type of electric motors | $7,710 | $11,858 |
$3,757
20,006
kWh
|
$3,953
-
kW-mo/yr
|
- | |
| 09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $50,714 | $22,284 |
$19,670
104,738
kWh
|
$31,044
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $987,708 | $1,140,973 |
$226,796
1,207,648
kWh
|
$616,912
-
kW-mo/yr
|
$144,000
-
gal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs