| Assessment Year | 2025 |
|---|---|
| Principal Product | Gloves |
| NAICS | 326299: All Other Rubber Product Manufacturing |
| SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 60 |
| Plant Area |
19,770
ft2
|
| Annual Production | 209,000
pieces
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $320,540 | 1,037,218 |
kWh
|
$0.31 |
| Electricity Demand | $157,394 | 2,370 |
kW-mo/yr
|
$66.42 |
| Natural Gas | $38,520 | 3,272 |
MMBtu
|
$11.77 |
| TOTAL YEARLY COSTS | $516,454 | |||
| RECOMMENDED SAVINGS* | $387,039 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $298,549 | $273,844 |
$156,277
505,750
kWh
|
$142,272
-
kW-mo/yr
|
|
| 02 | 2.3141: Use battery storage for demand control | $20,905 | $894 |
$(-2,113.6)
(-6,840)
kWh
|
$23,019
-
kW-mo/yr
|
|
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,779 | - |
$1,779
5,757
kWh
|
- | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,099 | $2,437 |
$6,253
20,235
kWh
|
$1,846
-
kW-mo/yr
|
|
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $14,398 | $3,518 |
$11,116
35,974
kWh
|
$3,282
-
kW-mo/yr
|
|
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,220 | $1,016 |
$1,714
5,546
kWh
|
$506
-
kW-mo/yr
|
|
| 07 | 2.4223: Install direct acting units in place of compressed air pressure system in safety system | $19,984 | $1,400 |
$19,984
64,673
kWh
|
- | |
| 08 | 2.7233: Use properly designed and sized hvac equipment | $21,106 | $91,450 |
$11,587
37,497
kWh
|
$9,519
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $387,039 | $374,559 |
$206,595
668,592
kWh
|
$180,444
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs