ITAC Assessment: SD0643
ITAC logo
ITAC Assessment: SD0643
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Insulated Copper and Specialty Wire
NAICS 331420: Copper Rolling, Drawing, Extruding, and Alloying
SIC 3357: Drawing and Insulating of Nonferrous Wire
Sales Range $100
M
to 500
M
# of Employees 76
Plant Area 60,733
ft2
Annual Production 500,000
units
Production Hrs. Annual 4,667
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $70,634 425,003
kWh
Electricity Demand $43,888 2,789
kW-mo/yr
Electricity Fees $18,244 -
Natural Gas $52,094 3,104
MMBtu
TOTAL YEARLY COSTS $184,860
RECOMMENDED SAVINGS* $85,100 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,673

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $338 $424 $298
1,791
kWh
$40
-
kW-mo/yr
-
02 2.9114: Use solar heat to make electricty $55,833 $125,021 $44,500
267,750
kWh
$11,333
-
kW-mo/yr
-
03 2.3141: Use battery storage for demand control $11,390 - $(-5,609.0)
(-33,750)
kWh
$16,999
-
kW-mo/yr
-
04 2.2211: Use optimum temperature $6,846 - - - $6,846
-
MMBtu
05 2.1121: Use insulation in furnaces to facilitate heating / cooling $2,058 $4,196 $1,554
9,346
kWh
$504
-
kW-mo/yr
-
06 2.1121: Use insulation in furnaces to facilitate heating / cooling $6,190 $4,926 $4,673
28,115
kWh
$1,517
-
kW-mo/yr
-
07 2.4231: Reduce the pressure of compressed air to the minimum required $489 $250 $489
2,944
kWh
- -
08 2.4223: Install direct acting units in place of compressed air pressure system in safety system $1,956 $2,000 $1,956
11,772
kWh
- -
TOTAL RECOMMENDED $85,100 $136,817 $47,861
287,968
kWh
$30,393
-
kW-mo/yr
$6,846
-
MMBtu
TOTAL IMPLEMENTED $7,673 $674 $787
4,735
kWh
$40
-
kW-mo/yr
$6,846
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs