Assessment Year | 2023 |
---|---|
Principal Product | Insulated Copper and Specialty Wire |
NAICS | 331420: Copper Rolling, Drawing, Extruding, and Alloying |
SIC | 3357: Drawing and Insulating of Nonferrous Wire |
Sales Range | $100 M to 500M |
# of Employees | 76 |
Plant Area |
60,733
ft2
|
Annual Production | 500,000
units
|
Production Hrs. Annual | 4,667
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $70,634 | 425,003 |
kWh
|
$0.17 |
Electricity Demand | $43,888 | 2,789 |
kW-mo/yr
|
$15.74 |
Electricity Fees | $18,244 | - |
|
- |
Natural Gas | $52,094 | 3,104 |
MMBtu
|
$16.78 |
TOTAL YEARLY COSTS | $184,860 | |||
RECOMMENDED SAVINGS* | $85,100 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,673 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $338 | $424 |
$298
1,791
kWh
|
$40
-
kW-mo/yr
|
- | |
02 | 2.9114: Use solar heat to make electricty | $55,833 | $125,021 |
$44,500
267,750
kWh
|
$11,333
-
kW-mo/yr
|
- | |
03 | 2.3141: Use battery storage for demand control | $11,390 | - |
$(-5,609.0)
(-33,750)
kWh
|
$16,999
-
kW-mo/yr
|
- | |
04 | 2.2211: Use optimum temperature | $6,846 | - | - | - |
$6,846
-
MMBtu
|
|
05 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $2,058 | $4,196 |
$1,554
9,346
kWh
|
$504
-
kW-mo/yr
|
- | |
06 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $6,190 | $4,926 |
$4,673
28,115
kWh
|
$1,517
-
kW-mo/yr
|
- | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $489 | $250 |
$489
2,944
kWh
|
- | - | |
08 | 2.4223: Install direct acting units in place of compressed air pressure system in safety system | $1,956 | $2,000 |
$1,956
11,772
kWh
|
- | - | |
TOTAL RECOMMENDED | $85,100 | $136,817 |
$47,861
287,968
kWh
|
$30,393
-
kW-mo/yr
|
$6,846
-
MMBtu
|
||
TOTAL IMPLEMENTED | $7,673 | $674 |
$787
4,735
kWh
|
$40
-
kW-mo/yr
|
$6,846
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs