Assessment Year | 2023 |
---|---|
Principal Product | Fiberglass Bus and Train Components |
NAICS | 327212: Other Pressed and Blown Glass and Glassware Manufacturing |
SIC | 3229: Pressed and Blown Glass and Glassware, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 105 |
Plant Area |
55,000
ft2
|
Annual Production | 500,000
units
|
Production Hrs. Annual | 2,160
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $55,775 | 520,805 |
kWh
|
$0.11 | |
Electricity Demand | $70,314 | 3,117 |
kW-mo/yr
|
$22.56 | |
Electricity Fees | $6,152 | - |
|
- | |
Natural Gas | $36,746 | 1,607 |
MMBtu
|
$22.87 | |
Waste Disposal Costs | |||||
Other Liquid (haz) | $346,680 | 3,240 |
gal
|
$107.00 | |
TOTAL YEARLY COSTS | $515,667 | ||||
RECOMMENDED SAVINGS* | $153,671 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $46,189 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,553 | $19,352 |
$2,985
27,873
kWh
|
$3,497
-
kW-mo/yr
|
$71 | - | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,834 | $21,620 |
$2,184
20,394
kWh
|
$3,650
-
kW-mo/yr
|
- | - | - | |
03 | 2.4223: Install direct acting units in place of compressed air pressure system in safety system | $2,501 | $11,000 |
$2,501
23,348
kWh
|
- | - | - | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,929 | $16,830 |
$1,708
15,952
kWh
|
$2,221
-
kW-mo/yr
|
- | - | - | |
05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,325 | $8,632 |
$772
7,203
kWh
|
$2,256
-
kW-mo/yr
|
- |
$(-702.5)
-
MMBtu
|
- | |
06 | 2.2511: Insulate bare equipment | $252 | $1,171 |
$75
705
kWh
|
$177
-
kW-mo/yr
|
- | - | - | |
07 | 2.9114: Use solar heat to make electricty | $46,189 | $70,634 |
$19,117
178,500
kWh
|
$27,072
-
kW-mo/yr
|
- | - | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $628 | $1,441 |
$291
2,718
kWh
|
$337
-
kW-mo/yr
|
- | - | - | |
09 | 2.1133: Adjust burners for efficient operation | $3,019 | $7,800 | - | - | - |
$3,019
-
MMBtu
|
- | |
10 | 2.7232: Replace existing hvac unit with high efficiency model | $2,049 | $6,650 |
$760
7,095
kWh
|
$1,289
-
kW-mo/yr
|
- | - | - | |
11 | 2.2511: Insulate bare equipment | $347 | $332 |
$65
609
kWh
|
$282
-
kW-mo/yr
|
- | - | - | |
12 | 3.1121: Use more efficient adhesive applicators | $80,045 | $6,600 | - | - | - | - |
$80,045
-
gal
|
|
TOTAL RECOMMENDED | $153,671 | $172,062 |
$30,458
284,397
kWh
|
$40,781
-
kW-mo/yr
|
$71 |
$2,317
-
MMBtu
|
$80,045
-
gal
|
||
TOTAL IMPLEMENTED | $46,189 | $70,634 |
$19,117
178,500
kWh
|
$27,072
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs