| Assessment Year | 2023 |
|---|---|
| Principal Product | Antibodies, Cell Therapies |
| NAICS | 325414: Biological Product (except Diagnostic) Manufacturing |
| SIC | 2836: Biological Products, Except Diagnostic Substances |
| Sales Range | $10 M to 50M |
| # of Employees | 75 |
| Plant Area |
42,000
ft2
|
| Annual Production | 100,000
units
|
| Production Hrs. Annual | 2,295
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $241,273 | 1,863,698 |
kWh
|
$0.13 | |
| Electricity Demand | $237,440 | 8,584 |
kW-mo/yr
|
$27.66 | |
| Natural Gas | $83,581 | 6,230 |
MMBtu
|
$13.42 | |
| Waste Disposal Costs | |||||
| Water Usage | $4,308 | 504,000 |
Tgal
|
$0.009 | |
| TOTAL YEARLY COSTS | $566,602 | ||||
| RECOMMENDED SAVINGS* | $112,789 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $100,326 | $408,646 |
$46,694
360,570
kWh
|
$53,632
-
kW-mo/yr
|
- | |
| 02 | 2.2441: Preheat boiler makeup water with waste process heat | $868 | $4,212 | - | - |
$868
-
MMBtu
|
|
| 03 | 2.4224: Upgrade controls on compressors | $348 | $1,355 |
$348
2,687
kWh
|
- | - | |
| 04 | 2.2623: Minimize condenser cooling water temperature | $8,765 | $13,961 |
$4,146
32,015
kWh
|
$4,619
-
kW-mo/yr
|
- | |
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $2,482 | $5,000 | - | - |
$2,482
-
MMBtu
|
|
| TOTAL RECOMMENDED | $112,789 | $433,174 |
$51,188
395,272
kWh
|
$58,251
-
kW-mo/yr
|
$3,350
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs