| Assessment Year | 2023 |
|---|---|
| Principal Product | Steel fabricated racks, cabinets, accessories for Data Center, IT infrastructure |
| NAICS | 331110: Iron and Steel Mills and Ferroalloy Manufacturing |
| SIC | 3399: Primary Metal Products, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 225 |
| Plant Area |
100,000
ft2
|
| Annual Production | 100,000
units
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $187,218 | 1,349,508 |
kWh
|
$0.14 |
| Electricity Demand | $118,035 | 2,886 |
kW-mo/yr
|
$40.90 |
| Electricity Fees | $14,838 | - |
|
- |
| Natural Gas | $450,444 | 31,188 |
MMBtu
|
$14.44 |
| TOTAL YEARLY COSTS | $770,535 | |||
| RECOMMENDED SAVINGS* | $21,674 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,075 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,107 | $5,169 |
$1,229
8,862
kWh
|
$878
-
kW-mo/yr
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,290 | $1,500 |
$3,795
27,330
kWh
|
$495
-
kW-mo/yr
|
- | - | |
| 03 | 2.2414: Use waste heat from hot flue gases to preheat | $8,718 | $11,910 | - | - |
$8,718
-
MMBtu
|
- | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $1,715 | $1,161 |
$1,209
8,721
kWh
|
$506
-
kW-mo/yr
|
- | - | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $998 | $4,300 |
$628
4,530
kWh
|
$370
-
kW-mo/yr
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,070 | $828 |
$659
4,752
kWh
|
$389
-
kW-mo/yr
|
- | $22 | |
| 07 | 2.2414: Use waste heat from hot flue gases to preheat | $2,776 | $7,884 | - | - |
$2,776
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $21,674 | $32,752 |
$7,520
54,195
kWh
|
$2,638
-
kW-mo/yr
|
$11,494
-
MMBtu
|
$22 | ||
| TOTAL IMPLEMENTED | $7,075 | $3,489 |
$5,663
40,803
kWh
|
$1,390
-
kW-mo/yr
|
- | $22 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs