| Assessment Year | 2016 |
|---|---|
| Principal Product | Inter-ocular lenses |
| NAICS | 339112: Surgical and Medical Instrument Manufacturing |
| SIC | 3841: Surgical and Medical Instruments and Apparatus |
| Sales Range | $10 M to 50M |
| # of Employees | 180 |
| Plant Area |
80,000
ft2
|
| Annual Production | 2,000
pieces
|
| Production Hrs. Annual | 5,772
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $179,075 | 2,326,939 |
kWh
|
$0.077 |
| Electricity Demand | $86,936 | 5,059 |
kW-mo/yr
|
$17.18 |
| Electricity Fees | $16,513 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $125,266 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7232: Replace existing hvac unit with high efficiency model | $55,828 | $139,240 |
$39,666
515,151
kWh
|
$16,162
-
kW-mo/yr
|
- | - | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $41,516 | $13,343 |
$22,007
285,805
kWh
|
$24,739
-
kW-mo/yr
|
$(-5,230.0)
-
MMBtu
|
- | |
| 03 | 4.212: Adopt in-house material generation | $9,790 | $15,235 |
$(-8.0)
(-94)
kWh
|
- | - | $9,798 | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,076 | $29,064 |
$5,109
66,357
kWh
|
$3,668
-
kW-mo/yr
|
- | $299 | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,155 | $5,524 |
$2,820
36,622
kWh
|
$1,335
-
kW-mo/yr
|
- | - | |
| 06 | 2.7111: Reduce illumination to minimum necessary levels | $1,558 | $760 |
$1,057
13,748
kWh
|
$501
-
kW-mo/yr
|
- | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,189 | $1,000 |
$782
10,153
kWh
|
$407
-
kW-mo/yr
|
- | - | |
| 08 | 2.7135: Install occupancy sensors | $883 | $2,510 |
$883
11,462
kWh
|
- | - | - | |
| 09 | 2.7261: Install timers and/or thermostats | $629 | $344 |
$629
8,166
kWh
|
- | - | - | |
| 10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $362 | $200 |
$362
4,696
kWh
|
- | - | - | |
| 11 | 2.4133: Use most efficient type of electric motors | $280 | $767 |
$191
2,475
kWh
|
$89
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $125,266 | $207,987 |
$73,498
954,541
kWh
|
$46,901
-
kW-mo/yr
|
$(-5,230.0)
-
MMBtu
|
$10,097 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs