ITAC Assessment: UD0455
ITAC logo
ITAC Assessment: UD0455
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product storage drums, kegs
NAICS
n/a
SIC 3412: Metal Shipping Barrels, Drums, Kegs, and Pails
Sales Range $10
M
to 50
M
# of Employees 88
Plant Area 81,000
ft2
Annual Production 900,000
pieces
Production Hrs. Annual 4,500
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $223,136 3,356,682
kWh
Natural Gas $165,000 52,678
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $93,367 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $66,513

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Administrative Changes Savings
01 2.3212: Optimize plant power factor $5,558 $9,500 $5,558
-
kWh
- - - -
02 2.8113: Purchase gas directly from a contract gas supplier $18,240 $80,000 - - - - $18,240
03 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $19,024 $17,000 $16,908
302,755
kWh
- - - $2,116
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,503 $2,989 $1,503
17,878
kWh
- - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $380 $4,400 $330
4,982
kWh
- - - $50
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,695 $1,320 $1,760
27,843
kWh
$(-65.0)
-
MMBtu
- - -
07 2.2424: Use heat in flue gases to preheat products or materials $4,193 $3,000 - $4,193
-
MMBtu
- - -
08 3.4155: Meter waste water $1,754 $600 - - $1,754
-
Tgal
- -
09 3.2136: Use "wash-less" processing equipment $41,020 $8,000 $2,370
37,222
kWh
- - $38,650
-
gal
-
TOTAL RECOMMENDED $93,367 $126,809 $28,429
390,680
kWh
$4,128
-
MMBtu
$1,754
-
Tgal
$38,650
-
gal
$20,406
TOTAL IMPLEMENTED $66,513 $98,820 $9,688
65,065
kWh
$(-65.0)
-
MMBtu
- $38,650
-
gal
$18,240
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs