Assessment Year | 2016 |
---|---|
Principal Product | Major Aircraft Components |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 160 |
Plant Area |
250,000
ft2
|
Annual Production | 8,000
pieces
|
Production Hrs. Annual | 5,625
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $325,590 | 4,580,660 |
kWh
|
$0.071 |
Electricity Demand | $241,792 | 11,625 |
kW-mo/yr
|
$20.80 |
Electricity Fees | $107,964 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $203,208 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $34,279 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.7232: Replace existing hvac unit with high efficiency model | $117,397 | $321,940 |
$65,109
915,734
kWh
|
$52,288
-
kW-mo/yr
|
- | |
02 | 3.1192: Reduce scrap production | $22,801 | $25,619 |
$13,088
184,084
kWh
|
$9,713
-
kW-mo/yr
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $18,641 | $1,700 |
$13,317
187,282
kWh
|
$5,324
-
kW-mo/yr
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,638 | $43,142 |
$8,038
113,050
kWh
|
$7,039
-
kW-mo/yr
|
$561 | |
05 | 2.7261: Install timers and/or thermostats | $8,651 | $1,032 |
$8,651
121,680
kWh
|
- | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,000 | $200 |
$6,000
84,389
kWh
|
- | - | |
07 | 2.4239: Eliminate or reduce compressed air usage | $5,400 | $1,300 |
$1,136
15,979
kWh
|
$4,264
-
kW-mo/yr
|
- | |
08 | 2.7135: Install occupancy sensors | $4,725 | $7,800 |
$4,725
66,833
kWh
|
- | - | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,286 | $4,076 |
$1,614
22,705
kWh
|
$672
-
kW-mo/yr
|
- | |
10 | 2.2628: Utilize a less expensive cooling method | $1,512 | $200 |
$1,079
15,181
kWh
|
$433
-
kW-mo/yr
|
- | |
11 | 2.7134: Use photocell controls | $157 | $185 |
$120
1,682
kWh
|
$37
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $203,208 | $407,194 |
$122,877
1,728,599
kWh
|
$79,770
-
kW-mo/yr
|
$561 | ||
TOTAL IMPLEMENTED | $34,279 | $44,842 |
$21,355
300,332
kWh
|
$12,363
-
kW-mo/yr
|
$561 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs