Assessment Year | 2011 |
---|---|
Principal Product | Office and Store Fixtures |
NAICS | 337215: Showcase, Partition, Shelving, and Locker Manufacturing |
SIC | 2542: Office and Store Fixtures, Partitions, Shelving, and Lockers, Except Wood |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
184,000
ft2
|
Annual Production | 1,000,000
units
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $89,206 | 899,565 |
kWh
|
$0.099 |
Electricity Demand | $67,159 | 5,272 |
kW-mo/yr
|
$12.74 |
Natural Gas | $82,873 | 12,344 |
MMBtu
|
$6.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,303 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $667 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7134: Use photocell controls | $152 | - |
$87
881
kWh
|
$65
-
kW-mo/yr
|
- | |
02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $11,615 | $5,000 |
$(-423.0)
(-4,267)
kWh
|
- |
$12,038
-
MMBtu
|
|
03 | 2.4239: Eliminate or reduce compressed air usage | $3,820 | $2,500 |
$3,820
38,470
kWh
|
- | - | |
04 | 2.2123: Insulate feedwater tank | $443 | $400 |
$443
66
kWh
|
- | - | |
05 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $5,758 | $7,385 |
$5,758
58,040
kWh
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $515 | $983 |
$296
2,979
kWh
|
$219
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $22,303 | $16,268 |
$9,981
96,169
kWh
|
$284
-
kW-mo/yr
|
$12,038
-
MMBtu
|
||
TOTAL IMPLEMENTED | $667 | $983 |
$383
3,860
kWh
|
$284
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs