| Assessment Year | 1983 |
|---|---|
| Principal Product | GREASES, OILS, FLUIDS |
| NAICS |
n/a
|
| SIC | 2992: Lubricating Oils and Greases |
| Sales Range | $1 M to 5M |
| # of Employees | 98 |
| Plant Area |
n/a
|
| Annual Production | 7,000,000
lb
|
| Production Hrs. Annual | 2,134
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $34,679 | 401,817 |
kWh
|
$0.086 |
| Natural Gas | $81,734 | 16,525 |
MMBtu
|
$4.95 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $24,343 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $24,343 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,312 | $1,500 | - |
$3,312
-
MMBtu
|
|
| 02 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $2,960 | $800 | - |
$2,960
-
MMBtu
|
|
| 03 | 2.2113: Repair or replace steam traps | $2,673 | $2,000 | - |
$2,673
-
MMBtu
|
|
| 04 | 2.2122: Install / repair insulation on condensate lines | $1,624 | $400 | - |
$1,624
-
MMBtu
|
|
| 05 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $916 | $800 | - |
$916
-
MMBtu
|
|
| 06 | 2.2136: Install / repair insulation on steam lines | $9,791 | $5,000 | - |
$9,791
-
MMBtu
|
|
| 07 | 2.7221: Lower temperature during the winter season and vice-versa | $2,308 | $132 |
$759
8,792
kWh
|
$1,549
-
MMBtu
|
|
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $759 | $1,026 |
$759
8,792
kWh
|
- | |
| TOTAL RECOMMENDED | $24,343 | $11,658 |
$1,518
17,584
kWh
|
$22,825
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $24,343 | $11,658 |
$1,518
17,584
kWh
|
$22,825
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs