Assessment Year | 2015 |
---|---|
Principal Product | latex emulsion |
NAICS | 325211: Plastics Material and Resin Manufacturing |
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | less than $500 k |
# of Employees | 40 |
Plant Area |
196,200
ft2
|
Annual Production | 80,001
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $308,943 | 4,107,349 |
kWh
|
$0.075 |
Electricity Demand | $205,059 | 7,674 |
kW-mo/yr
|
$26.72 |
Electricity Fees | $40,433 | - |
|
- |
Natural Gas | $117,425 | 15,302 |
MMBtu
|
$7.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $184,075 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $118,874 | $425,000 |
$114,844
2,080,500
kWh
|
$66,800
-
kW-mo/yr
|
$(-62,770.0)
-
MMBtu
|
|
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $15,403 | $14,111 |
$15,403
204,833
kWh
|
- | - | |
03 | 2.7261: Install timers and/or thermostats | $15,039 | $2,275 |
$15,039
199,992
kWh
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,837 | $1,500 |
$5,665
75,336
kWh
|
$3,172
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,591 | $14,085 |
$5,047
67,113
kWh
|
$2,544
-
kW-mo/yr
|
- | |
06 | 2.2414: Use waste heat from hot flue gases to preheat | $7,238 | $10,050 | - | - |
$7,238
-
MMBtu
|
|
07 | 2.7111: Reduce illumination to minimum necessary levels | $6,323 | $1,580 |
$4,133
54,953
kWh
|
$2,190
-
kW-mo/yr
|
- | |
08 | 2.2414: Use waste heat from hot flue gases to preheat | $3,817 | $12,575 | - | - |
$3,817
-
MMBtu
|
|
09 | 2.7135: Install occupancy sensors | $953 | $1,745 |
$953
12,668
kWh
|
- | - | |
TOTAL RECOMMENDED | $184,075 | $482,921 |
$161,084
2,695,395
kWh
|
$74,706
-
kW-mo/yr
|
$(-51,715.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs