| Assessment Year | 2014 |
|---|---|
| Principal Product | Lighting Fixtures |
| NAICS | 335122: Commercial, Industrial, and Institutional Electric Lighting Fixture Manufacturing |
| SIC | 3646: Commercial, Industrial, and Institutional Electric Lighting Fixtures |
| Sales Range | less than $500 k |
| # of Employees | 125 |
| Plant Area |
193,000
ft2
|
| Annual Production | 80,001
pieces
|
| Production Hrs. Annual | 3,835
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $77,369 | 925,197 |
kWh
|
$0.084 |
| Electricity Demand | $83,587 | 3,877 |
kW-mo/yr
|
$21.56 |
| Electricity Fees | $12,251 | - |
|
- |
| Natural Gas | $18,749 | 2,550 |
MMBtu
|
$7.35 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $23,833 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,419 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7111: Reduce illumination to minimum necessary levels | $7,747 | $8,360 |
$4,286
51,276
kWh
|
$3,461
-
kW-mo/yr
|
|
| 02 | 2.7135: Install occupancy sensors | $7,664 | $12,000 |
$7,664
91,672
kWh
|
- | |
| 03 | 2.4226: Use / purchase optimum sized compressor | $4,939 | $15,269 |
$2,733
32,691
kWh
|
$2,206
-
kW-mo/yr
|
|
| 04 | 2.7134: Use photocell controls | $2,811 | $8,510 |
$2,002
23,949
kWh
|
$809
-
kW-mo/yr
|
|
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $434 | $1,400 |
$252
2,996
kWh
|
$182
-
kW-mo/yr
|
|
| 06 | 2.6218: Turn off equipment when not in use | $238 | $200 |
$225
2,687
kWh
|
$13
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $23,833 | $45,739 |
$17,162
205,271
kWh
|
$6,671
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $8,419 | $9,960 |
$4,763
56,959
kWh
|
$3,656
-
kW-mo/yr
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs